Water Reclamation                           2018-2022                   Capital Improvements Program       Schedule for Five Year Period
             Special assessment Bonds = a                                      Abatement District = ad                             Olmsted County = c Electric Utility =  eu Federal Funds =  f Flood Control Reserves =  fr                                              
                     Food & Beverage Tax = fb                                          Local Gov't Aid = ga              General Obligation Bonds = go Lodging Tax =  lt MN State Aid - Streets =  ms Operating Trfs - fr Storm Water =  os                                              
       Operating Trfs-fr General Fund = ot                   Operating Trfs-fr Sewer Utility = ow                               Private Funds = p Project Reserves =  r GO Revenue Bonds =  rb Retained Earnings = re                                              
                                     State Funds = s                          Sn/Sewer Availability Chg = sa                              Sales Tax DMC = sd State DMC Funds =  sm Sales Tax 2013 =  st Storm Water Mgmt Chg =  sw                                              
                                          Tax Levy = t                     Traffic Improvement Dist Chg = td                                Tax Increments = ti Operating Trfs - fr Other Funds = to Water Availability Chg =  wa Water Utility =  wu                                              
 2002-2017
Sort Map # Project Description Proj # Total Budget CIP Bdgt Amts 2018 2019 2020 2021 2022 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Totals
      0
1 1 WRP Equipment Replacement 4343                600,000             240,000 re             120,000 re               80,000 re               80,000 re               80,000 re re      80,000       80,000      80,000 re 240000
1       0
2 2 Sanitary Sewer Collection System Model 4332            1,150,000             400,000 re             150,000 re             150,000 re             150,000 re             150,000 re             150,000 re re    200,000    200,000 re 400000
2      
3 3 Waste Treatment Plant Facilities Plan update 4325            1,400,000             800,000 re             600,000 re re    100,000    700,000 800000
3       0
4 4 HPO Plant Upgrade            4,000,000              4,000,000 re re 0
4       0
5 5 Roof Replacement Project            1,200,000              1,200,000 re re 0
5       0
6 6 Nitrogen Sidestream Removal            4,500,000              4,500,000 re re 0
6       0
7 7 Treatment Facility Process Improvement            2,000,000              2,000,000 re 0
7      
                                                                      0        
Total Cost            14,850,000          1,440,000               870,000            4,230,000            1,430,000            4,730,000            2,150,000  
Sources of Funds
Retained Earnings re          14,850,000          1,440,000 re             870,000 re          4,230,000 re          1,430,000 re          4,730,000 re          2,150,000 re
Total Sources of Funds            14,850,000          1,440,000               870,000            4,230,000            1,430,000            4,730,000            2,150,000   1440000
Total of NEW FUNDING requests            870,000         4,230,000         1,430,000         4,730,000         2,150,000
Total adjustments to prior years' funding authorizations                        -                          -                          -                          -                          -  
Total Cost             870,000          4,230,000          1,430,000          4,730,000          2,150,000
                   -  
                 -