RESOLUTION
BE IT RESOLVED by the Common Council of the City of Rochester that the City to approve
the amendment of the current professional services agreement with SEH and Barr Engineering as
outlined in the attached supplemental letter agreement for additional engineering services totaling
$27,379.65. Funding will come from the previously approved City project J6608 that is funded by
the Storm Water Utility.
The Mayor and City Clerk are authorized and directed to execute this agreement on behalf
of the City.
PASSED AND ADOPTED BY THE COMMON COUNCIL OF THE CITY OF
ROCHESTER, MINNESOTA, THIS __________ DAY OF _______________, 2018.
___________________________________
PRESIDENT OF SAID COMMON COUNCIL
ATTEST: __________________________
CITY CLERK
APPROVED THIS _____ DAY OF ______________________, 2018.
__________________________________
MAYOR OF SAID CITY
(Seal of the City of
Rochester, Minnesota)
Res15\\ProfServ\\SEH.21
February 11, 2018RE:City of Rochester
Five Year Stormwater Agreement
Rocky CreekStabilization
City CIP No. 16
Supplemental Letter Agreement SW-11B
SEH Project Number ROCHE 132729
Mr. Troy R. Erickson, P.E.
Storm Water Engineer and Project Manager
Rochester Public Works
th
201 4Street SE, Room 108
City of Rochester
Rochester, MN 55904-7373
DearMr. Erickson:
®
Short Elliott Hendrickson Inc. (SEH)appreciates the opportunity to help the City address this important
project. Supplemental Letter Agreement No. SW-11dated May 10, 2016 and approval by the City Council
on May 2016 pertained to preliminary designfor Rocky Creek Phase 3 Stream Stabilization.Supplemental
Letter Agreement 11A approved on November 21, 2016 addresses final design and contract documents.
This Supplemental Letter Agreement 11B is based on additional services on the part of our subconsultant
Barr Engineering.
BACKGROUND
Rocky Creek Ravine stream stability issues were investigated in 2011 as part of a feasibility study
completed by Yaggy-Colby and Associates (now SEH). Bank erosion and channel degradation could
eventually impact two sanitary sewer crossings beneath the ravine and contribute to sediment loading in
the South Fork Zumbro River.
In May 2016, the SEH-Barr team was authorized to complete the preliminary design for creek
stabilization and develop a scope of services for final design and the development of contract documents.
In early August, Barr completed a Basis of Design report for Rocky Creek, Following an internal review,
the report was forwarded to City staff on August 9, 2016.
Engineers|Architects|Planners| Scientists
Short Elliott Hendrickson Inc., 717 Third Avenue SE, Suite 101,Rochester,MN55904-7373
SEH is 100% employee-owned|sehinc.com|507.288.6464|800.325.2055|888.908.8166fax
Mr. Troy R. Erickson
February 11, 2018
Page 2
In November of 2016,the SEH-Barr team was authorized to complete final design and contract
documentsfor stabilizing Rocky Creek. Construction documents were anticipated to be complete by
February 17, 2017 and construction was to occur in 2017.
The following summarizes progress on the project:
February 9, 2017 –Preliminary design drawings were provided to the City.
February 21, 2017 –Plan Review Meeting
February 21, 2017 –Revised schedule providedwith 90% plans on April 3, 2017
March 31, 2017 –Barr at 80% of budget.
April 4, 2017 –Barr made direct request to City staff for two week extension
April 21, 2017 –Additional Survey requested.
May 9, 2017 –Preferred option identified; Barr indicates that they will need an amendment.
June 6, 2017 –City repeats interest in building project in 2017. 90% plans expected June 16.
June 16, 2017 –90% plans delivered.
June 22, 2017 –City indicates that construction should be delayed until 2018.
August 2, 2017 –Design review meeting
August 25, 2017 –90% plans submitted for review.
September 8, 2017Receive City Comments on 90% Plans
October 27, 2017Complete Construction Documents
BASIS OF COMPENSATION
Barr Engineering served as principal investigator/designerfor this project. To date, Barr hadbeen
authorized up to $50,730to prepare the feasibility study, design and plans and specifications. To date,
Barr has billed $50,710.14and hasspent $78,089.700 as of January 26, 2108.Barr has discussed the
increase in cost with youon January 3, 2018(email).The primary reasons for the cost overrun are that (1)
the design effort requiredmore effort than originally anticipated, and (2) the design schedule took longer
than planned due to additional design iterations necessaryto match the project scope to the construction
budget.
We are requesting that the contract amount be amended to cover the cost over-runs by Barr Engineering.
Compensation shall be on an hourly basis, based on the actual hours worked for SEH personnel assigned
to the project, plus reimbursable expenses. The cost estimate is based on the project scope and schedule
identified herein.
With the requested amendment of $27,379.65, the overall contract amount for this project will be
$91,879.65.
Mr. Troy R. Erickson
February 11, 2018
Page 3
SUMMARY
This Supplemental Letter Agreement shall be the basis of work by SEH on the project described in this
letter. If you are in agreement with the terms, please execute this Supplemental Letter Agreement with
proper signatures and return one original to our offices.
We look forward to continuing our work with the City of Rochester.
Sincerely,
SHORT ELLIOTT HENDRICKSON INC.
Mark Lobermeier, PE
Senior Principal
Client Service Manager
Accepted this _______ day of _______, 2018
City of Rochester
By: ________________________________
Title: ________________________________
Rochester, Minnesota
Rocky Creek Stream Stabilization February 8, 2017
Exhibit A
Project Cost
Our estimated cost for completing the project is as follows:
TaskEstimated Cost
I.Additional Services for Design and Construction Documents
$27,379.65
(Barr Engineering)
TOTAL$27,379.65
Project Summary
Major TasksAgreementSEHBarrTotal
Feasibility ReportSW-11–May 2016$10,700$12,800$23,500
Design and Construction SW-11A –November $3,070$37,930$41,000
Documents2016
Addition Design ServicesCurrent Request$0$27,379.65$27,379.65
Total$13,770$78,109.65$91,879.65
Lunde,
Tollefson, Nypan, Burggraff, Kretschmer, Mohseni, Nielsen,
Kalmes, Waln, Howard, Fitzgerald,
Allison
KinelyNyssaJacobMarkOmidPaul
ArthurJosephAdamEric
ARKJJW2AKHEPF
Subtotal
$190.00 $105.00 $85.00 $115.00 $95.00 $84.38 $125.00 $160.00 $160.00 $175.00 Subtotal LaborExpensesProject Ttotal
$140.26
Hours
PICPMDesign Eng.CADSupportTech IIICons/AdvCons/AdvCons/Adv
Job 1 - Design8.237.1131.658.20.57.30.80.20.70.6245.2$26,594.00 $18.15$26,612.15
Job 2 - Specifications061.17.1$767.50 $767.50
Project Subtotal8.237.1137.658.20.57.30.81.1252.3$27,361.50 $18.15 $27,379.65
Contingency
Project Total$27,379.65