RESOLUTION
BE IT RESOLVED by the Common Council of the City of Rochester that the City Execute
Change Order #3 with Kraus-Anderson Construction for the US Customs/ Terminal Building
Project. The purpose of this change order is to
1. Pull $216,615.58 out of the Kraus Anderson contract so that the airport can use
those funds to purchase the required IT equipment and office furniture for the US
Customs offices directly without having to go through Kraus Anderson.
Combines funds remaining in the various allocations that were set up in the contract
documents so that they can be spent on remaining project related items.
2. Extends contract time for Allocation #7 (Finishes) to 11/30/2018 to account for a
longer lead time to secure matching floor tile.
The Change Order results in a contract credit of $216,615.58 that will in turn be spent on required
IT equipment and office furniture for US Customs. The new contract amount will be
$11,090,831.78. Local: #6942, State 5501-225 FAA 3-27-0084-36-16.
The Mayor and the City Clerk are authorized and directed to execute the change order on
behalf of the City.
PASSED AND ADOPTED BY THE COMMON COUNCIL OF THE CITY OF
ROCHESTER, MINNESOTA, THIS __________ DAY OF _______________, 2018.
___________________________________
PRESIDENT OF SAID COMMON COUNCIL
ATTEST: __________________________
CITY CLERK
APPROVED THIS _____ DAY OF ______________________, 2018.
___________________________________
MAYOR OF SAID CITY
(Seal of the City of
Rochester, Minnesota)
Res15\\Changeorder\\Airport3