Loading...
HomeMy WebLinkAbout2020_06 Summary - COR DMC TB & WFCity of Rochester, Minnesota, Destination Medical Center Targeted Business, Workforce Participation, Prevailing Wage and Buy American Steel June 2020 Summary Submitted by Jorrie Johnson, July 27, 2020 Please find the Construction and the Professional Services & Construction Administration Targeted Business (TB), Workforce Participation, Prevailing Wage and Buy American Steel June 2020 reports attached. Construction Targeted Business, Goal 4% (7% for Construction and 4% for Heavy Construction approved 6/15/2020) A. Total Project Costs: $362,019,833 B. Total Targeted Business contracts: $26,061,160 C. Targeted Business on contract average result: 7.2% D. Payments made to Targeted Businesses in June 2020: $307,186. Workforce Participation, Goals: Minorities 4% (15% approved June 15, 2020), Women 6% A. Alatus Housing – 2nd Street project workforce participation: 1. Minority participation: 19.2%, 2. Women participation: 3.3% B. 6th & 7th Avenue project 1. Challenges meeting goals. Minority 2.4%, Women 1.3% 2. Continue discussing diverse hiring practices with A-1 Excavating C. Heart of the City, March 1 – May 31 2020 1. Total hours: 6,547 2. Minority hours: 536, 8.2% a. Carl Bolander and Sons: 528 hours 3. Women hours (goal 6%): 102, 1.6% a. Krause Anderson: 102 hours D. Overall Results 1. Combined Minority Workforce Participation is 15.3% 2. Combined Women Workforce Participation is only 3.4% (under goal) Prevailing Wage (PW) A. Projects in LCPtracker (January – June 2020) UpNet Hrs LCPt Hrs Total Hrs Violations Alatus Berkman Apartments 522,013 69,868 591,881 3 Civic on First/Hyatt House 26,576 46,140 72,716 10 Heart of the City 6,547 1 City Loop Bike Lane Project J8903 2,384 0 1st Street NW Sanitary Sewer Diversion J7830 980 0 B. Hours in LCPtracker Total Employee Hours Rochester Hours Apprentice Hours Journeyman Hours Rochester Apprentice Hours 138,453 22,278 30,125 108,327 7,233 16% 5.% Buy American Steel Future Made in American mill receipts will be stored in LCPtracker. Past receipts from UpNET will be stored in City of Rochester Laserfische. Professional Services & Construction Administration Targeted Business, Goal 4% (7% approved June 15, 2020) A. Total Project Costs: $ 17,899,597 B. Total Targeted Business contracts: $ 1,286,438 C. Targeted Business on contract average result: 7.2% Workforce Participation, Goals: Minorities 4% (15% approved June 15, 2020), Women 6% A. TOD study for workforce participation starting for hours worked through June 2020. a. Total hours: 4,366 b. Minority hours: 436, 10% c. Women hours: 2,857, 65.4% B. SRF A&E Rapid Transit J8707 (PN 12839.00) a. Total hours: 1,079 b. Minority hours: 235, 21.8% c. Women hours: 455, 42.2% C. Overall Results a. Minorities: 7.2% b. Women: 35.3% Targeted Business and Workforce Participation Plan Updates A. Revising budget request B. Develop incentives > penalties plan over the summer C. Creating Good Faith Efforts evaluation standards D. Communicating with Lynn Littlejohn about Discovery Square Two TB goals