HomeMy WebLinkAboutResolution No. 273-21 - Resolution - 2022-27 Capital Improvement Plan (CIP)
RESOLUTION
Adopting the 2022-2027 Capital Improvement Plan (CIP).
BE IT RESOLVED by the Common Council of the City of Rochester, Minnesota, that the
City adopt the 2022-2027 Capital Improvement Plan for the City as set forth in writing in the
appended document, and the individual projects listed therein.
PASSED AND ADOPTED BY THE COMMON COUNCIL OF THE CITY OF
ROCHESTER, MINNESOTA, THIS __________ DAY OF _______________, 2021.
___________________________________
PRESIDENT OF SAID COMMON COUNCIL
ATTEST: __________________________
CITY CLERK
APPROVED THIS _____ DAY OF ______________________, 2021.
___________________________________
MAYOR OF SAID CITY
(Seal of the City of
Rochester, Minnesota)
Appendix
2022-2027 CIP Budget Master
Adopted Expenditures
2002-2021 2022-2027
Major Expenditure Categories Totals Totals 2022 2023 2024 2025 2026 2027
CIP Bdgt Amts
Airport 14,735,000 210,000 14,525,000 70,000 - 10,135,000 4,320,000 - -
Parks 43,765,519 23,403,519 20,362,000 5,106,250 4,085,750 3,100,000 2,515,000 2,765,000 2,790,000
Golf 698,000 168,000 530,000 75,000 80,000 85,000 90,000 100,000 100,000
Recreation Center 1,750,000 - 1,750,000 625,000 625,000 125,000 125,000 125,000 125,000
Graham Arena 2,358,957 2,233,727 125,230 125,230 - - - - -
Mayo Civic Center 4,042,265 779,665 3,262,600 849,600 914,600 374,600 374,600 374,600 374,600
Major Streets 101,331,852 19,193,700 82,138,152 15,593,948 9,382,204 12,393,000 18,202,000 13,962,000 12,605,000
Traffic 14,384,430 935,000 13,449,430 400,000 5,850,000 3,049,430 350,000 1,400,000 2,400,000
Pedestrian Facilities 24,444,700 10,002,700 14,442,000 2,010,000 2,660,000 2,210,000 3,007,000 2,230,000 2,325,000
Mass Transit 64,910,657 48,078,124 16,832,533 4,187,500 3,930,113 4,090,239 2,568,681 1,436,000 620,000
Parking 45,750,000 41,322,000 4,428,000 513,000 500,000 1,605,000 430,000 700,000 680,000
Sewer and Water 39,350,000 11,875,000 27,475,000 4,495,000 6,375,000 3,585,000 3,820,000 6,550,000 2,650,000
Storm Water 26,713,750 12,318,750 14,395,000 2,380,000 2,685,000 2,030,000 1,725,000 2,590,000 2,985,000
Water Reclamation 70,260,000 3,660,000 66,600,000 5,100,000 29,100,000 17,100,000 100,000 15,100,000 100,000
Flood Control 38,580,000 9,135,000 29,445,000 1,380,000 23,625,000 1,285,000 1,635,000 785,000 735,000
Destination Medical Center 350,459,094 101,753,745 248,705,349 62,594,888 64,046,184 56,164,378 17,992,799 32,684,644 15,222,456
Downtown Dvlpmnt/Tax Abatemnt District 4,725,000 3,750,000 975,000 250,000 225,000 125,000 125,000 125,000 125,000
Rochester Econ Dvlpmnt Authority - - - - - - - - -
Fire 3,106,810 1,310,310 1,796,500 240,000 326,500 310,000 295,000 265,000 360,000
Police 27,911,000 26,630,000 1,281,000 397,000 397,000 397,000 30,000 30,000 30,000
Library 4,626,160 3,226,376 1,399,784 349,739 116,049 251,100 136,849 161,350 384,697
Administration 4,370,114 2,352,114 2,018,000 468,000 348,000 293,000 293,000 318,000 298,000
Totals 888,273,308 322,337,730 565,935,578 107,210,155 155,271,400 118,707,747 58,134,929 81,701,594 44,909,753
Sources of Funds
Tax Levy 78,356,573 28,212,243 50,144,330 7,594,330 8,015,600 8,255,100 8,502,100 8,757,100 9,020,100
Local Government Aid 471,724 471,724 - - - - - - -
Tax Abatements 3,350,000 3,350,000 - - - - - - -
Tax Increment - - - - - - - - -
Operating Transfer - fr General Fund 1,893,110 1,893,110 - - - - - - -
Operating Transfer - fr General Fund Sales Tax 1,014,068 1,014,068 - - - - - - -
Operating Transfer - fr Other Funds 7,283,846 5,978,268 1,305,578 301,105 66,786 402,052 87,876 112,411 335,348
Operating Transfer - fr Sewer Utility 21,699,500 7,630,500 14,069,000 1,989,000 1,701,000 3,876,000 2,451,000 2,101,000 1,951,000
Operating Transfer - fr Storm Wtr Utility 2,886,500 217,000 2,669,500 1,168,250 300,250 600,250 600,250 250 250
Flood Control Reserves 26,674,000 14,099,000 12,575,000 1,380,000 6,955,000 1,085,000 1,635,000 785,000 735,000
Electric Utility 3,673,000 1,831,000 1,842,000 1,819,500 4,500 4,500 4,500 4,500 4,500
Water Utility 3,385,500 121,500 3,264,000 876,500 100,500 635,500 750,500 500,500 400,500
Retained Earnings 86,614,357 49,807,950 36,806,407 6,342,500 7,918,523 5,142,048 4,838,736 8,231,400 4,333,200
Olmsted County 3,529,534 1,246,828 2,282,706 174,884 1,096,513 510,298 150,223 300,189 50,599
State 70,886,994 28,095,894 42,791,100 15,930,450 21,752,750 817,500 3,640,400 650,000 -
Municipal State Aid for Streets 44,443,152 3,995,000 40,448,152 9,634,948 7,207,204 2,765,000 3,891,000 8,150,000 8,800,000
State Loan Fund - - - - - - - - -
Federal 101,564,232 26,824,906 74,739,326 5,539,300 27,675,911 32,641,170 7,276,545 1,129,600 476,800
Sales Tax 2013 300,000 300,000 - - - - - - -
Sales Tax DMC 72,698,454 43,436,230 29,262,224 6,455,616 6,634,831 4,815,878 3,698,799 3,784,644 3,872,456
Food & Beverage Tax - - - - - - - - -
State DMC Funds 125,252,880 41,668,515 83,584,365 18,130,902 17,523,000 10,580,463 10,600,000 22,900,000 3,850,000
Transit Aid County DMC 19,116,303 3,649,600 15,466,703 4,155,534 4,542,581 3,368,588 - 400,000 3,000,000
Transit Aid State DMC 40,741,157 5,474,400 35,266,757 10,388,836 11,356,451 8,421,470 - 600,000 4,500,000
Lodging Tax - - - - - - - - -
Private Funds 5,951,500 2,267,500 3,684,000 529,000 290,000 2,340,000 140,000 140,000 245,000
Water Availability Charges - - - - - - - - -
Sewer Availability Charges 1,129,430 - 1,129,430 - - 1,129,430 - - -
Storm Water Area Mgmt Charge 4,095,000 1,885,000 2,210,000 40,000 300,000 660,000 150,000 465,000 595,000
Traffic Improvement District Fees 100,000 - 100,000 - - 100,000 - - -
Special Assessment Bonds 21,168,200 7,700,200 13,468,000 1,625,000 1,595,000 3,145,000 2,363,000 2,345,000 2,395,000
General Obligation Bonds 20,735,000 9,160,000 11,575,000 6,575,000 5,000,000 - - - -
General Obligation Revenue Bonds 82,000,000 23,000,000 59,000,000 5,000,000 22,000,000 17,000,000 - 15,000,000 -
Project reserves 37,259,294 9,007,294 28,252,000 1,559,500 3,235,000 10,412,500 7,355,000 5,345,000 345,000
2020 Parks Referendum - - - - - - - - -
Unfunded Projects - - - - - - - - -
Totals 888,273,308 322,337,730 565,935,578 107,210,155 155,271,400 118,707,747 58,134,929 81,701,594 44,909,753
Airport 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
280,000
1 Terminal Building Elevator Overhaul 210,000 r 70,000 r 1
2 Parking Lot Reconstruction/Upgrades - Design & Construction. Reserves to be
transferred from J6950 (Airport Future Construction).
4,455,000
9,000,000
3 Hangar Design & Construction
4 Snow Removal Equipment - Blower. Reserves to be transferred from J6950 (Airport
Future Construction). 1,000,000
6999
Total Cost 14,735,000 210,000 70,000
Sources of Funds
Project reserves r 11,807,500 70,000
r
State s 2,927,500
s
Total Sources of Funds 14,735,000 70,000
Unfunded Projects - - -
Total of NEW FUNDING requests 70,000
Total adjustments to prior years' funding authorizations
-
Total Cost 70,000
Schedule For Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
67,500 s 2,160,000 s
67,500 r 2,160,000 r
9,000,000 r
700,000 s
300,000 r
- 10,135,000 4,320,000 - -
r r r
9,367,500 r 2,160,000 r
767,500 2,160,000
s s s s s
10,135,000 4,320,000
- - - -
-
- 10,135,000 4,320,000 - -
-
- - - -
10,135,000 4,320,000 - -
-
Parks 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga
General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re
State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw
Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
1 Park Referendum 2020 - $2M additional tax levy approved by voters in the 2020
election. Funds will be used on a variety of park and recreation projects.
3062 2,000,000 t 1
11,700,000 (675,000) pr 1
2,000,000 t
3 Game Haven Active Nature Sports Park - Design and Development of Gamehaven
Park - Entrance Drive (possible to the top of the hill), small parking lot, play area,
perimeter trail around the 95 acre area for mt bike and ski, 18 hole disc golf, snow
making for 2K snow made ski loop on the new property, utilities (electric/sewer/water
service) and possibly rest rooms. Project Reserves will be transferred from Future
Construction J1994.
3053
350,000 t 5
4,956,000 15,000 p 5
150,000 t
15,000 p
200,000 r
5 Annual diseased tree removal and reforestation of city parks/public lands and
boulevards. 2019/20 work includes Urban Forest Master Plan and the Urban Forest
Tree Canopy Assessment along with EAB management. Natural Resource Inventory.
2022 NOTE: State funds identified are based on potential grants that will be sought.
3033 150,000 t 2
3,081,519 150,000 t 25,000 s 2
25,000 s
6 McQuillan Lighting - Replace lights and poles. 10 Years of payments. 2962 150,000 pr 7
1,080,000
7 Neighborhood Playground Replacement. - Annual replacement of playground
equipment, etc. throughout the Park System 3061 50,000 t 12
450,000
50,000 t
9 Neighborhood Park Development - Annual investment in new parks throughout the park
system based on new development (playground equipment, trails, shelters, etc.)
3060
50,000 t 13
50,000 p
50,000 t
13
1,150,000
50,000 p
10 Replacement of safety surfacing materials to semi-permanent type rubber surface at
various parks. Reserves to be transferred from each quadrant of park dedication
reserves as funds are available.
75,000 r 8
925,000
75,000 r
11 Quarry Hill Park projects include: Master Plan improvements, asset preservation and
asset expansion. Construction of additional access to historical caves and cave erosion
management, replacement of trail and entrance walk to Nature Center, construct pond
trail, renovate island landscaping, new roof, sound control and finish in the Safe Room,
canoe launch, HVAC and invasive vegetation control. Additionally, shelter and
playground improvement together with Nature Play are needed at the park.
2913 50,000 t 14
1,225,000
50,000 t
15 Plummer House improvements. Asset preservation of the Historical Plummer House of
the Arts. Work is based on the Facility Master Plan for the property and the Water
Tower Assessment document. Work includes the following deferred maintenance over
the next several years: Water Tower Phase I improvements $300K, Phase II
Improvements $200K, Deferred maintenance interior and exterior improvements
(roofing, plastering, mold abatement, stairwell repairs, re-lay path, retaining wall #4
repair) $100K, year 3 improvements $200K, and year 5 improvements $100K
2980
150,000 s 9
2,109,000
100,000 r 9
150,000 s
150,000 pr
9
383,000 f
9
Schedule For Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
2,000,000 t 2,000,000 t 2,000,000 t 2,000,000 t 2,000,000 t
(525,000) pr (550,000) pr (150,000) pr (250,000) pr (150,000) pr
150,000 t
15,000 p 15,000 p 15,000 p 15,000 p 15,000 p
150,000 t 150,000 t 150,000 t 200,000 t 400,000 t
150,000 pr 150,000 pr 150,000 pr 150,000 pr 150,000 pr
50,000 t 50,000 t 50,000 t 50,000 t 50,000 t
50,000 t 50,000 t 50,000 t 75,000 t 100,000 t
75,000 p 75,000 p 75,000 p 75,000 p 100,000 p
75,000 r 75,000 r 75,000 r 75,000 r 75,000 r
50,000 t 50,000 t 50,000 t 75,000 t 50,000 t
150,000 t
50,000 s 50,000 s 50,000 s 50,000 s
100,000 pr
Parks 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
16 Cascade Lake Park - Master Plan improvements. This includes design and
construction of a pavilion, amphitheater, performance facilities, picnic shelters, restroom
facilities, play areas, park access and landscaping. NOTE: A portion of the 2024 tax
levy amount will be used to replenish project reserves that were used in the design
phase in 2021.
2981 17,089,000
471,000 r
375,000
pr 6
339,500 t 6
1,318,750 s 6
Total Cost
43,765,519 3,436,000 5,106,250
Sources of Funds
Electric Utility eu 1,750,000 eu eu
Federal f 383,000 f 383,000 f
Flood Control Reserves fr 2,964,000 fr fr
Private Funds p 1,865,000 65,000 p 65,000 p
Project reserves r 2,440,000 746,000 r 175,000 r
State s 12,191,000 175,000 s 1,493,750 s
Tax Levy t 22,172,519 2,450,000 t 2,989,500 t
Total Sources of Funds
43,765,519 3,436,000 5,106,250
- - -
Unfunded Projects
Total of NEW FUNDING requests 5,781,250
Total adjustments to prior years' funding authorizations (675,000)
Total Cost
5,106,250
Schedule For Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
375,000 pr 400,000 pr
339,500 t 435,000 t
s
1,231,250
4,085,750 3,100,000 2,515,000 2,765,000 2,790,000
eu eu eu eu eu
f f f f f
fr fr fr fr fr
90,000 p 90,000 p 90,000 p 90,000 p 115,000 p
75,000 r 75,000 r 75,000 r 75,000 r 75,000 r
1,281,250 s 50,000 s 50,000 s 50,000 s s
2,639,500 t 2,885,000 t 2,300,000 t 2,550,000 t 2,600,000 t
4,085,750 3,100,000 2,515,000 2,765,000 2,790,000
- - - - -
4,610,750 3,650,000 2,665,000 3,015,000 2,940,000
(525,000) (550,000) (150,000) (250,000) (150,000)
4,085,750 3,100,000 2,515,000 2,765,000 2,790,000
Golf 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
2 Golf Course System improvements and enhancements.
698,000
2908 25,000 t 75,000 t 1
Total Cost 698,000 25,000 75,000
Sources of Funds
Tax Levy t 698,000 25,000 75,000
t t
Total Sources of Funds 698,000 25,000 75,000
Unfunded Projects - - -
Total of NEW FUNDING requests 75,000
Total adjustments to prior years' funding authorizations -
Total Cost 75,000
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
80,000 t 85,000 t 90,000 t 100,000 t 100,000 t
80,000 85,000 90,000 100,000 100,000
80,000 85,000 90,000 100,000
t t t t 100,000 t
100,000
80,000 85,000 90,000 100,000
- - - - -
80,000 85,000 90,000 100,000 100,000
- - - - -
80,000 85,000 90,000 100,000 100,000
Recreation Center 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
1
Roof Replacement/Restoration (Project Reserves from PY Park Referendum funds
available J3062) 750,000
125,000 r 1
2
Repayment of internal borrowing for Air Handling System Replacement to project
J1036 - City Facilities Capital Reserve. 1,000,000
500,000
t 2
Total Cost 1,750,000 - 625,000
Sources of Funds
Project reserves r 750,000 r 125,000 r
Tax Levy t 1,000,000 500,000
t t
Total Sources of Funds 1,750,000 625,000
Unfunded Projects - - -
Total of NEW FUNDING requests 625,000
Total adjustments to prior years' funding authorizations -
Total Cost 625,000
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
125,000 r 125,000 r 125,000 r 125,000 r 125,000 r
500,000 t
625,000 125,000 125,000 125,000 125,000
125,000 125,000 125,000 125,000 125,000
r r r r r
500,000
t t t t t
625,000 125,000 125,000 125,000 125,000
- - - - -
625,000 125,000 125,000 125,000 125,000
- - - - -
625,000 125,000 125,000 125,000 125,000
Graham Arena 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
1 City contribution to Graham Arena Four is approximately $100,000 per year for 15 years,
beginning in '07. Final payment occurs in 2022.
2864 130,910 t 125,230 t 1
1,471,457
(25,000) r 1
(25,000) r
2 Graham Arena improvements including replacement of bleachers in GA 1, adding handicap
seating in GA 1, replace exterior door in GA 1-2-3, and update scoreboards in GA 1-2-3.
Replacement of facility doors, restroom fixtures and lobby area upgrades to include paint and
furniture. (City's share provided by reserves from J2864).
2964 25,000 r 25,000 r 2
887,500
Total Cost 2,358,957 130,910 125,230
Sources of Funds
Olmsted County c 262,500 c c
Local Government Aid ga 122,500 ga ga
Private Funds p 262,500 p p
Project reserves r 15,000 r r
Tax Levy t 1,696,457 130,910 125,230
t t
Total Sources of Funds 2,358,957 130,910 125,230
Unfunded Projects - - -
Total of NEW FUNDING requests 150,230
Total adjustments to prior years' funding authorizations -
Total Cost 150,230
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
- - - - -
c c c c c
ga
ga ga ga ga
p p p p p
r
r r r r
t
t t t t
- - - - -
- - - - -
- - - - -
- - - - -
Mayo Civic Center 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
1 Rochester Art Center and Rochester Civic Theatre facilities
354,600
2,127,600
t 1
2
Physical Plant: general plant improvements
120,000 20,000 r
3
3
General Facility: Service lot security updates (2022); AHU bipolar ionization
completion (2022); campus radio communications system update (2022); upgrade
locks to electronic readers (2023) 710,000 150,000 360,000 r
r 2
4
Rochester Civic Theatre: Theatre lighting update (2022); AHU replacement - end of
709,665 25,000 65,000 r
t 4
life (2023)
5
Rochester Art Center: Lighting control update (2022); Network update (2023)
25,000 50,000 r
150,000 t
5
7
Exhibit Hall: Curtain replacement (2023)
25,000
9
Riverview Suites: install projectors/controls (2023)
200,000
Total Cost 4,042,265 200,000 849,600
Sources of Funds
Local Government Aid ga 30,000 ga ga
Operating Transfer - fr General Fund ot 111,066 ot ot
Project reserves r 1,285,000 150,000 495,000
r r
Tax Levy t 2,616,199 50,000 354,600
t t
Total Sources of Funds 4,042,265 200,000 849,600
Unfunded Projects - - -
Total of NEW FUNDING requests 849,600
Total adjustments to prior years' funding authorizations -
Total Cost 849,600
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
354,600 354,600 354,600 354,600 354,600
t t t t t
20,000 r 20,000 r 20,000 r 20,000 r 20,000 r
200,000 r
65,000 r
50,000 r
25,000 r
200,000 r
914,600 374,600 374,600 374,600 374,600
ga ga ga ga ga
ot ot ot ot ot
560,000 20,000 20,000 20,000 20,000
r r r r r
354,600 354,600 354,600 354,600 354,600
t t t t t
914,600 374,600 374,600 374,600 374,600
- - - - -
914,600 374,600 374,600 374,600 374,600
- - - - -
914,600 374,600 374,600 374,600 374,600
Major Streets 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Water Availability Chg = wa
Transit Aid State DMC = ts
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
21,923,700
900,000 t 900,000 t 1
1 Annual Bituminous Street Rehabilitation, Resurfacing and Preservation 2201
13,347,000 500,000 t
600,000 t 2
2 Annual Bituminous Street Reconstruction 2200
3 CIP debt repayment; $200,000 annually for ten years beginning in 2020, ending in
1,600,000 200,000 t
2029. 4844 200,000 t 3
11,023,948
320,000 ms
4 Reconstruct 65 St NW from 60 Ave NW to 50 Ave NW 9853 9,509,948 ms 4
780,000 os 4
414,000 p 4
5 RPU Marion Road Distribution Duct Project Along 9 St SE; reserves to be transferred
3,190,000
from J2200 7843 80,000 a 5
270,000 os 5
215,000 ow 5
670,000 wu 5
1,815,000 eu 5
140,000 r 5
1,000,000
6 Annual Bridge Rehabilitation
10,660,000
7 Reconstruct Broadway from Zumbro River Bridge to Elton Hills Drive 7341
Reconstruct 65 St NW from 50 Ave NW to 37 Ave NW 7,357,204
700,000 ms
8 9852
9 Reconstruct Center Street E from Zumbro Bridge to 11th Ave E. To be combined with
11th Ave E Intersection Improvements (J6063) budgeted at and adopted at $300,000
in previous 2020 Traffic CIP, for a total project cost of $4,480,000.
6063
4,480,000
10 Construct 64 St NW from 34 Ave NW to 37 Ave NW (per MnDOT Agreement). 2,800,000
11 Concrete Pavement Rehabilitation (CPR) Center St W from 16 Ave W to 6 Ave W.
Includes 11th Ave Intersection Improvements.
1,500,000
12 Reconstruct Shoppes on Maine (Maine Ave SE, Canal Pl SE, and 45th St SE)
4,150,000
Phase 1; Reserves to be transferred from J2200 7301
13 Reconstruct/Rehab 20 St SW from 1 Ave SW to Mayowood Road (CR125) and
intersection improvements. 9859 7,500,000
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
1,000,000 t 1,000,000 t 1,000,000 t 1,000,000 t 1,000,000 t
825,000 t 1,623,000 t 2,932,000 t 3,162,000 t 3,205,000 t
200,000 t 200,000 t 200,000 t 200,000 t 200,000 t
200,000 t 200,000 t 200,000 t 200,000 t 200,000 t
500,000 r 2,580,000 f 2,580,000 f
700,000 r 700,000 r
600,000 os 600,000 os
600,000 ow 600,000 ow
350,000 wu 350,000 wu
250,000 a 250,000 a
6,007,204 ms
300,000 os
100,000 ow
100,000 wu
150,000 p
140,000 ms 2,922,000 ms
400,000 wu
300,000 ow
418,000 a
500,000 a
100,000 td
2,200,000 p
1,350,000 ms
4,150,000 r
300,000 ms 5,950,000 ms
600,000 a
150,000 ow
200,000 wu
Major Streets 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Water Availability Chg = wa
Transit Aid State DMC = ts
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
1,200,000
14 Clearwater Rd NW/55 St NW Intersection Safety Improvements.
15 Concrete Pavement Rehabilitation (CPR) 4 St SE from 11 Ave SE to 19 Ave SE
(Phase 2)
7335 900,000
8,700,000
16 Reconstruct of 11 Ave E from 4 St SE to Silver Creek (Bridge No 55505)
Total Cost 101,331,852 2,620,000 15,593,948
Sources of Funds
80,000
a a
Special Assessment Bonds a 5,882,300
c c
Olmsted County c 350,000
1,815,000
eu eu
Electric Utility eu 1,815,000
f f
Federal f 5,160,000
1,020,000 9,509,948
ms ms
Municipal State Aid for Streets ms 35,699,152
1,050,000
os os
Operating Transfer - fr Storm Water Utility os 2,550,000
ot ot
Operating Transfer - fr General Fund ot 1,464,016
215,000
ow ow
Operating Transfer - fr Sewer Utility ow 2,765,000
ox ox
Operating Transfer - fr General Fund Sales Tax ox 225,079
414,000
p p
Private Funds p 2,764,000
140,000
r r
Project reserves r 10,940,000
s s
State s 600,000
1,600,000 1,700,000
t t
Tax Levy t 28,247,305
td td
Traffic Improvement District Fees td 100,000
670,000
wu wu
Water Utility wu 2,770,000
Total Sources of Funds 101,331,852 2,620,000 15,593,948
Unfunded Projects - - -
Total of NEW FUNDING requests 15,593,948
Total adjustments to prior years' funding authorizations -
Total Cost 15,593,948
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
100,000 ms 150,000 ms
100,000 c 250,000 c
600,000 s
100,000 ms 800,000 ms
400,000 ow 400,000 ow
300,000 wu 400,000 wu
6,600,000 ms
600,000 a
9,382,204 12,393,000 18,202,000 13,962,000 12,605,000
a 750,000 a 668,000 a 600,000 a 600,000 a
c c 100,000 c 250,000 c c
eu eu eu eu eu
f 2,580,000 f 2,580,000 f f f
6,007,204 ms 1,490,000 ms 3,422,000 ms 6,900,000 ms 6,600,000 ms
300,000 os 600,000 os 600,000 os os os
ot ot ot ot ot
100,000 ow 600,000 ow 900,000 ow 550,000 ow 400,000 ow
ox ox ox ox ox
150,000 p 2,200,000 p p p p
500,000 r 700,000 r 4,850,000 r r r
s s s 600,000 s s
2,225,000 t 3,023,000 t 4,332,000 t 4,562,000 t 4,605,000 t
td 100,000 td td td td
100,000 350,000 750,000 500,000 400,000
wu wu wu wu wu
9,382,204 12,393,000 18,202,000 13,962,000 12,605,000
- - - - -
9,382,204 12,393,000 18,202,000 13,962,000 12,605,000
- - - - -
9,382,204 12,393,000 18,202,000 13,962,000 12,605,000
Traffic 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
1 Traffic calming program in residential neighborhoods. 1,660,000
8208 50,000 t 150,000 t 1
2 Viola Rd NE & Century Hills Dr NE Intersection Improvements
6013 2,250,000 125,000 c 2
125,000 ms 2
3
600,000
Roadway Corridor Lighting
4 Broadway Ave S and 12th St SW/SE (US 14) Intersection Improvements. Project
Reserves will be transferred from Broadway Turnback funds J2202.
3,500,000
6064 3,124,430 75,000 ms
5 4th St SE & 19th Ave SE Intersection Improvements
6 55th St NW & 50th Ave NW Intersection Improvements
6065 1,750,000
7 2nd St NW and 3rd/4th Aves NW Intersection Improvements
500,000
8 Civic Center Dr NE and West Silver Lake Dr NE Intersection Improvements
500,000
9 Elton Hills Dr NW and West River Pkwy NW Intersection Improvements
500,000
Total Cost 14,384,430 125,000 400,000
Sources of Funds
a a
Special Assessment Bonds a 410,000
125,000
c c
Olmsted County c 1,125,000
75,000 ms 125,000 ms
Municipal State Aid for Streets ms 6,475,000
r r
Project reserves r 1,850,000
s s
State s 1,750,000
sa sa
Sewer Availability Charges sa 1,129,430
sw sw
Storm Water Area Mgmt Charge sw 360,000
50,000 150,000
t t
Tax Levy t 1,150,000
wu wu
Water Utility wu 135,000
Total Sources of Funds 14,384,430 125,000 400,000
Unfunded Projects - - -
Total of NEW FUNDING requests 400,000
Total adjustments to prior years' funding authorizations
-
Total Cost 400,000
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
150,000 t 150,000 t 150,000 t 150,000 t 200,000 t
1,000,000 c
1,000,000 ms
200,000 ms 200,000 ms 200,000 ms
1,750,000 r
1,750,000 s
1,275,000 ms
1,129,430 sa
135,000 wu
360,000 sw
250,000 ms 1,500,000 ms
500,000 ms
500,000 ms
500,000 ms
5,850,000 3,049,430 350,000 1,400,000 2,400,000
a a a a a
1,000,000 c c c c c
1,200,000 ms 1,275,000 ms 200,000 ms 1,250,000 ms 2,200,000 ms
1,750,000 r r r r r
1,750,000 s s s s s
sa 1,129,430 sa sa sa sa
sw 360,000 sw sw sw sw
150,000 t 150,000 t 150,000 t 150,000 t 200,000 t
135,000
wu wu wu wu
5,850,000 3,049,430 350,000 1,400,000 2,400,000
- - - - -
5,850,000 3,049,430 350,000 1,400,000 2,400,000
- - - - -
5,850,000 3,049,430 350,000 1,400,000 2,400,000
Pedestrian Facilities 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
1 Annual Sidewalk program - Annual construction and reconstruction of sidewalks at
various locations. Recommendation is to inspect 10% of the City's sidewalks each
year (historical average is less than 5%).
8307 16,120,900 200,000 t 200,000 t 1
1,500,000 a 1
1,000,000 a
2 Annual Sidewalk Gap Fill Program - Construct missing sidewalk infill areas. 4649 1,075,000 15,000 t 15,000 t 3
45,000 a 45,000 a 3
Annual Pedestrian Ramp Program - Construct pedestrian ramps at various locations -
3
new development area. Reserves to be transferred from J8209 (Ped Facility Charges).
520,000
8209 50,000 p 50,000 p 2
4 Annual ADA Transition Plan - Federal Compliance Ped Ramp Replacement program.
Includes other pedestrian safety improvements. 625,000
4665 50,000 t t 4
50,000
5 Safe Routes to Schools
4632 175,000 25,000 t 25,000 t 5
6 Pedestrian Crossing at Development Service & Infrastructure Center (DSIC) and 41 St
NW and sidewalk repairs & improvements. Project Reserves to be transferred from
J1023.
62,500 t 6
1,898,400
r 6
62,500
710,000
7 Annual Bituminous Path Reconstruction
8 Construct Trail along CP Railroad from 16th St SE to 20th St SE (This is phase 2 of
Broadway S Trail project).
2,373,400
4692
9 Construct Pedestrian facilities on 37th St NW from 18 Ave NW to W River Pkwy NW
947,000
4714
Total Cost 24,444,700 1,385,000 2,010,000
Sources of Funds
1,045,000 1,545,000
a a
Special Assessment Bonds a 14,125,900
f f
Federal f 2,064,800
ga ga
Local Government Aid ga 30,000
ms ms
Municipal State Aid for Streets ms 2,269,000
50,000 50,000
p p
Private Funds p 420,000
62,500
r r
Project reserves r 217,000
st st
Sales Tax 2013 st 300,000
290,000 352,500
t t
Tax Levy t 5,018,000
Total Sources of Funds 24,444,700 1,385,000 2,010,000
Unfunded Projects - - -
Total of NEW FUNDING requests 2,010,000
Total adjustments to prior years' funding authorizations
-
Total Cost 2,010,000
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
200,000 t 200,000 t 200,000 t 200,000 t 200,000 t
1,550,000 a 1,600,000 a 1,650,000 a 1,700,000 a 1,750,000 a
15,000 t 15,000 t 15,000 t 15,000 t 15,000 t
45,000 a 45,000 a 45,000 a 45,000 a 45,000 a
50,000 p 50,000 p 50,000 p 50,000 p 50,000 p
50,000 t 50,000 t 50,000 t t t
50,000 50,000
25,000 t 25,000 t 25,000 t 25,000 t 25,000 t
t t t t t
125,000 125,000 125,000 145,000 190,000
240,000 f
360,000 t
100,000 t 269,000 ms
578,000 f
2,660,000 2,210,000 3,007,000 2,230,000 2,325,000
1,595,000 a 1,645,000 a 1,695,000 a 1,745,000 a 1,795,000 a
240,000 f f 578,000 f f f
ga ga ga ga ga
ms ms 269,000 ms ms ms
50,000 p 50,000 p 50,000 p 50,000 p 50,000 p
r r r r r
st st st st st
775,000 515,000 415,000 435,000 480,000
t t t t t
2,660,000 2,210,000 3,007,000 2,230,000 2,325,000
- - - - -
2,660,000 2,210,000 3,007,000 2,230,000 2,325,000
- - - - -
2,660,000 2,210,000 3,007,000 2,230,000 2,325,000
Mass Transit 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
1 Bus Stop Improvements
1,218,500
2092 t 3
250,000
24,000 re
2 Replacement Buses for Fixed Routes. This is for purchase of 6 replacement buses
each year in 2022 - 2024, 3 buses in 2025, 1 bus in 2026, and 1 bus in 2027. Based
on maintaining a 15-17 year lifecycle. The costs shown assumes diesel (add $300,000
per bus for electric). Delivery is 12-15 months from date of order or obligation. Budget
year is based on award date. The buses from 2022-2024 have approved federal and
state grants including CARES Act funding; 2024 is fully funded via CARES.
2091 f 1
38,388,997 2,472,000
re 1
309,000
1,680,000 f s 1
309,000
1,220,000 re
3 Expansion Buses for Fixed Routes - This project calls for the purchase of 1 - 40' bus
each year in 2022 through 2025. Budget year is based on award date. The 40' buses
have state and federal grants awarded based on diesel. Add $300,000 per bus for
electric which is not included in the grant. Delivery is 12-15 months from date of order.
2091 101,500 re 2
20,809,356
406,000 f 2
2,016,000 f
384,000 s
600,000 re
4 Paratransit Buses - Purchase replacement buses for ZIPS Dial-A-Ride 2091 3,946,404 re 4
34,000
f 4
178,300
s 4
127,700
5 Transit Signal Priority System- Installation at 10 intersections along two primary transit
network corridors. The signals are on 4th St SE from downtown to Rochester
Community Technical College, on 37th St NE/NW from West River Parkway NW to
18th Ave NW, and on 41st St NW from 18th Ave NW to 31st Ave NW also known as
the North Crosstown Corridor. Funds to be transferred from the 280 Transit Fund
reserves
547,400
2105
Total Cost 64,910,657 5,924,000 4,187,500
Sources of Funds
Federal f 37,606,382 3,696,000 f 3,056,300 f
Local Government Aid ga 254,614 ga ga
Operating Transfer - fr General Fund Sales Tax ox 788,989 ox ox
Project reserves r 498,456 r r
1,844,000
Retained Earnings re 3,972,407 re 444,500 re
436,700
State s 14,546,494 384,000 s s
Tax Levy t 3,834,719 t 250,000 t
Operating Transfer - Other Funds to
3,408,596
to to
64,910,657 5,924,000 4,187,500
Total Sources of Funds
Unfunded Projects - - -
Total of NEW FUNDING requests 4,187,500
Total adjustments to prior years' funding authorizations
-
Total Cost
4,187,500
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
t t t
250,000 250,000 250,000
24,000 re 24,000 re
f f f f
3,062,000 3,180,000 476,800 476,800
re 357,600 re re re
51,500 119,200 119,200
s 1,430,400 s
51,500
103,023 re 104,568 re 106,136 re
412,090 f 418,271 f 424,545 f
163,200 re
652,800 f
109,920 f
27,480 re
3,930,113 4,090,239 2,568,681 1,436,000 620,000
3,474,090 f 3,708,191 f 424,545 f 1,129,600 f 476,800 f
ga ga ga ga ga
ox ox ox ox ox
r r r r r
154,523 re 132,048 re 463,736 re 306,400 re 143,200 re
51,500 1,430,400
s s s s s
250,000 250,000 250,000
t t t t t
to
to to to to
3,930,113 4,090,239 2,568,681 1,436,000 620,000
- - - - -
3,930,113 4,090,239 2,568,681 1,436,000 620,000
- - - - -
3,930,113 4,090,239 2,568,681 1,436,000 620,000
Parking 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
1 Ramp #6 Restoration - This is a ramp restoration project planned 4 years out
from the ramp opening in 2019. Condition assessment in 2022 with repairs
focused on wear and tear, traffic toppings, etc.
2582 14,515,000 100,000 re 15,000 re 4
2580 5,920,000 20,000 re 3
2 First Street Ramp Restoration project per 4 year cycle
3 Civic Center Ramp - Restoration project per 4 year cycle.
2578 3,560,000 20,000 re 330,000 re 1
4 Third Street Ramp Restoration project per 4 year cycle.
2583 10,000,000 20,000 re 100,000 re 2
5 Charging Stations installed in public parking areas-Level 1 type-to be
144,000
2579 48,000 re 5
Second Street Ramp Restoration project per 4 year cycle. Ramp was built in
6
1962, restoration project will depend on status of riverfront redevelopment.
2594 2,860,000
7 Government Center Lot - Redesign with landscaping in 2024. (Olmsted
County to pay 46% of cost.)
2,050,000
2585
8 Center Street Ramp Restoration project per 4 year cycle
3,145,000
2592 400,000 re
New meter technologies. Continued enhancements, meter/pay station
9
updates, expansion of license plate recognition (LPR) etc. Approximately
1,300 on-street metered spaces and 950 lot spaces.
2595 3,526,000
10 Bicycle Parking Enhancements
30,000 15,000 re
Total Cost
45,750,000 555,000 513,000
Sources of Funds
Olmsted County c 742,800 c c
Retained Earnings re 38,893,200 555,000 513,000
re re
State s 6,052,000 s s
Tax Levy t 62,000
t t
Total Sources of Funds 45,750,000 555,000 513,000
Unfunded Projects - - -
Total of NEW FUNDING requests 513,000
Total adjustments to prior years' funding authorizations
-
Total Cost 513,000
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
50,000 re 20,000 re 330,000 re
330,000 re 20,000 re 330,000 re
20,000 re 330,000 re
20,000 re 330,000 re
20,000 re 330,000 re 20,000 re
54,000 re 540,000 re
46,000 c 460,000 c
25,000 re 375,000 re
250,000 re
15,000 re
500,000 1,605,000 430,000 700,000 680,000
46,000 460,000
c c c c c
454,000 re 1,145,000 re 430,000 re 700,000 re 680,000 re
s s s s s
t t t t t
500,000 1,605,000 430,000 700,000 680,000
- - - - -
500,000 1,605,000 430,000 700,000 680,000
- - - - -
500,000 1,605,000 430,000 700,000 680,000
Sewer and Water 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
Retained Earnings = re
GO Revenue Bonds = rb State Funds = s
Storm Water Mgmt Chg = sw
Sales Tax 2013 = st Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
1 Annual Program: Sanitary sewer rehabilitation & repair. Funding from Sewer Utility
Retained Earnings.
2133
16,500,000
1,500,000 ow 1,500,000 ow 1
8,000,000
2 Sanitary Sewer trunk line extension and up sizing 1,000,000 re 1,000,000 re 8
3 Update City of Rochester Sanitary Sewer Master Plan and Sewer Modeling Program.
Current plan was last updated in 1996.
4340 2,000,000 100,000 re 3
100,000 re
950,000 50,000 ow 50,000 ow 2
4 Sanitary sewer flow monitor upgrades and repair. Funding from Sewer Utility Retained
5 2nd St and 16th Ave SE Sewer Mtce Project 5
575,000
150,000 re
6 Silver Lake Siphon: Bridge at W Silver Lake Dr & 7th St NE 7
7829 3,100,000 100,000 re
1,500,000
7 E River Rd NE Sewer Mtce Project 225,000 re 1,275,000 re 4
420,000
8 7th and 7th NW Sewer Mtce Project 100,000 re 320,000 re 6
1,235,000
9 6th Ave and 16th St SW Sewer Mtce Project 7839
5,070,000
10 4th St SE Sewer Mtce Project
Total Cost 39,350,000 2,975,000 4,495,000
Sources of Funds
Operating Transfer - fr Sewer Utility ow 16,700,000 1,550,000 1,550,000
ow ow
General Obligation Revenue Bonds rb 1,000,000
rb rb
1,425,000 2,945,000
re re
Retained Earnings re 21,650,000
Total Sources of Funds 39,350,000 2,975,000 4,495,000
Unfunded Projects - - -
Total of NEW FUNDING requests 4,495,000
Total adjustments to prior years' funding authorizations
-
Total Cost 4,495,000
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
1,500,000 ow 1,500,000 ow 1,500,000 ow 1,500,000 ow 1,500,000 ow
1,000,000 re 1,000,000 re 1,000,000 re 1,000,000 re 1,000,000 re
100,000 re 100,000 re 100,000 re 100,000 re 100,000 re
50,000 ow 50,000 ow 50,000 ow 50,000 ow 50,000 ow
425,000 re
3,000,000 re
300,000 re 935,000 re
1,170,000 re 3,900,000 re
6,375,000 3,585,000 3,820,000 6,550,000 2,650,000
1,550,000 1,550,000 1,550,000 1,550,000 1,550,000
ow ow ow ow ow
rb rb rb rb rb
4,825,000 2,035,000 2,270,000 5,000,000
re re re re 1,100,000 re
6,375,000 3,585,000 3,820,000 6,550,000 2,650,000
- - - - -
6,375,000 3,585,000 3,820,000 6,550,000 2,650,000
- - - -
6,375,000 3,585,000 3,820,000 6,550,000 2,650,000
Storm Water 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Water Availability Chg = wa
Transit Aid State DMC = ts
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
2,200,000
300,000 re
1 Annual Program Funding for Land Acquisition 350,000 re 18
Annual Program: Funding for Addressing Historical Drainage Issues
2,227,500
2 6505 125,000 re
150,000 re 7
Annual Program: Funding for Conveyance System Repair
1,858,750
3 6504 150,000 re
150,000 re 6
4 Annual Program: Funding for Stormwater Management Facility Rehabilitation and
Repair
6503
2,377,500
125,000 re
125,000 re 8
Annual Program: Tree Planting within Stormwater Parcels
5 6667 300,000 25,000 re
25,000 re 15
Annual Program: Fund for Local Match on Grant Applications.
630,000
7 5,000 re
5,000 re 17
Stormwater Education Program Development Initiatives
8 6709
140,000 10,000 re
10,000 re 16
9 Regional Stormwater Detention/Flood Control Facility: Southeast Quadrant of 60 Ave
NW & 65 St NW
1,350,000
100,000 re 14
Stormwater Management Plan Update - Phase II
10 6601
600,000
400,000 re 9
11 Regional Stormwater Detention/Flood Control Facility Project: Construct regional
stormwater facility kr-p.1 (Reference Cascade Twp Section 7 Report Pond 40 or similar
alternative.) Initial expenditures for ROW and land acquisition funded from Flood
Control reserves.
6574
4,150,000
125,000 re
150,000 re 3
125,000 sw
250,000 fr
12 Groundwater Mitigation: Branch Ln NW and Hillsboro DR NW to Blossom St NW
200,000
200,000 re 10
13 Stormwater Management Facility Survey and Inspection
200,000
200,000 re 5
14 Groundwater Mitigation: Knollwood DR SE
125,000 - re
125,000 re 12
15 7th ST NE Storm Sewer Outfall Replacement at Silver Creek 6714
310,000 125,000 re
125,000 re 13
16 Groundwater Mitigation: Regent Ln SW to Apple Ridge Blvd SW
100,000
100,000 re 11
17 Stormwater Utility Fee Rate Study
75,000
75,000 re 4
18 Regional Stormwater Detention Facility Project: Construct regional stormwater
detention facility KR-P1.2 Kalmar Twp (Reference Cascade Twp Section 7 Report,
Pond 3 or similar alternative).
6519
1,325,000 150,000 re
50,000 re 2
150,000 sw
19 Stormwater Management Plan Reimbursements: Rose Harbor Estates City Pond 155.
400,000
40,000 sw
6632
40,000 sw 1
20 Flood Mitigation: Address flooding on 10th St SE between 4th Ave SE and 7th Ave SE
1,450,000
by installing sewer along 10th St SE from 6th Ave SE to Bear Creek.
1,350,000
21 40 ST NW Flood Mitigation 6713
22 Regional Stormwater Detention/Flood Control Facility Project: Phase 2 regional pond
50,000
for krp1.8c (Cascade Township Section 18).
1,410,000
Flood Mitigation: 12th ST SE at 3rd AVE SE
23 6685
1,075,000
24 Construct Hadley Valley Regional Stormwater Facility 6599
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
450,000 re 100,000 re 100,000 re 800,000 re 100,000 re
150,000 re 150,000 re 150,000 re 150,000 re 150,000 re
150,000 re 150,000 re 150,000 re 150,000 re 150,000 re
125,000 re 125,000 re 125,000 re 125,000 re 125,000 re
25,000 re 25,000 re 25,000 re 25,000 re 25,000 re
25,000 re 5,000 re 25,000 re 5,000 re 5,000 re
10,000 re 10,000 re 10,000 re 10,000 re 10,000 re
350,000 re 300,000 re
300,000 sw 300,000 sw
200,000 re
150,000 re
150,000 re 700,000 re 550,000 re
550,000 re
50,000 re
165,000 re 165,000 re 300,000 re 600,000 re
100,000 re 200,000 re 200,000 re
100,000 sw 200,000 sw 200,000 sw
Storm Water 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Water Availability Chg = wa
Transit Aid State DMC = ts
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
25 Flood Mitigation: Cascade Street NW and 13th Ave NW 6653 950,000
26 Construct Regional Stormwater Facility: 75th Street NW east of TH 52 (pond NW p3.3).
1,000,000
6555
27 Regional Stormwater Detention Facility: Construct regional stormwater detention facility
in northeast quadrant of Valley High Drive and 50th Ave NW within cca3.1.
6677 500,000
28 Flood Mitigation: Pinewood RD SE at 36th AVE SE 360,000
60,000 re
Total Cost 26,713,750 1,765,000 2,380,000
Sources of Funds
250,000 fr fr
Flood Control Reserves fr 2,000,000
p p
Private Funds p 140,000
1,200,000 re 2,340,000 re
Retained Earnings re 20,838,750
315,000 sw 40,000 sw
Storm Water Area Mgmt Charge sw 3,735,000
Total Sources of Funds 26,713,750 1,765,000 2,380,000
Unfunded Projects - - -
Total of NEW FUNDING requests 2,380,000
Total adjustments to prior years' funding authorizations
-
Total Cost 2,380,000
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
125,000 re 125,000 re 250,000 re
50,000 re 225,000 re 225,000 re
50,000 sw 225,000 sw 225,000 sw
10,000 re 170,000 re
40,000 sw 170,000 sw
80,000 p
300,000 re
2,685,000 2,030,000 1,725,000 2,590,000 2,985,000
fr fr fr fr fr
p p p p 80,000 p
2,385,000 re 1,730,000 re 1,575,000 re 2,125,000 re 2,310,000 re
300,000 sw 300,000 sw 150,000 sw 465,000 sw sw
595,000
2,685,000 2,030,000 1,725,000 2,590,000 2,985,000
- - - - -
2,685,000 2,030,000 1,725,000 2,590,000 2,985,000
-
- - - -
2,685,000 2,030,000 1,725,000 2,590,000
2,985,000
Water Reclamation 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
1 WRP Equipment Replacement 2
1,260,000
4343 100,000 re 100,000 re
2 Phase 2 Liquid Treatment Upgrade 5,000,000 rb 1
54,000,000 3,000,000 go
15,000,000
3 Phase 3 Solid Treatment Upgrade
Total Cost 70,260,000 3,100,000 5,100,000
Sources of Funds
General Obligation Bonds go 3,000,000 3,000,000 go go
General Obligation Revenue Bonds rb 59,000,000 rb 5,000,000 rb
Retained Earnings re 1,260,000 100,000 re 100,000 re
State s 7,000,000
s s
Total Sources of Funds 70,260,000 3,100,000 5,100,000
Unfunded Projects - - -
Total of NEW FUNDING requests
5,100,000
Total adjustments to prior years' funding authorizations
-
Total Cost 5,100,000
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
100,000 re 100,000 re 100,000 re 100,000 re 100,000 re
22,000,000 rb 17,000,000 rb
7,000,000 s
15,000,000 rb
29,100,000 17,100,000 100,000 15,100,000 100,000
go go go go go
22,000,000 rb 17,000,000 rb rb 15,000,000 rb rb
100,000 re 100,000 re 100,000 re 100,000 re 100,000 re
7,000,000
s s s s s
29,100,000 17,100,000 100,000 15,100,000 100,000
- - - - -
29,100,000 17,100,000 100,000 15,100,000 100,000
- - - - -
29,100,000 17,100,000 100,000 15,100,000 100,000
Flood Control 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
420,000
1 Annual River Bank and Reservoir Repair/Stabilization. 4856 25,000 fr 25,000 fr 1
4869 1,635,000 100,000 fr 100,000 fr 11
2 Create 90 acres of wetlands at WR-4 Reservoir.
Flood Control Management System (Reservoirs, weirs, levees, engineered channel) -
3
annual regulatory compliance actions with Operation & Maintenance plan.
70,000
4883 5,000 fr 5,000 fr 3
4 Flood Control Walls - joint maintenance and repair, including cleaning and re-caulking.
4882 725,000 75,000 fr 75,000 fr 7
4857 1,200,000 100,000 fr 100,000 fr 2
5 Annual Flood Control trail system - repairs and overlays.
4888 325,000 25,000 fr 25,000 4
6 Repaint / Recondition Flood Control Railing. fr
200,000
7 Replace reservoir monitoring equipment and gauges. 4887 10,000 fr 10,000 fr 6
4860 2,075,000 200,000 fr 200,000 fr 10
8 Cascade Creek stabilization from 16th Ave NW east to Civic Center Dr.
2,950,000
9 Zumbro River Bank Stabilization from 19th Street to 37th Street. 4861 300,000 fr 300,000 fr 9
400,000
10 Replace Flood Control Ped Lighting. 40,000 fr 40,000 fr 8
4,390,000
11 Remove sediment from Silver Lake, Cascade Lake, and Reservoirs. 4889 1,000,000 fr 500,000 fr 5
Silver Lake Sediment Removal, and Revitalization. Transfer from other funds would be
12
from Park and Rec for a portion of trail work. State bonding not secured. If not
received, the full project will not occur.
23,340,000
4889 800,000 fr
850,000 fr
13 Remove sediment from S. Zumbro River Levee to Hwy 14
Total Cost 38,580,000 2,680,000 1,380,000
Sources of Funds
Flood Control Reserves fr 21,710,000 2,680,000 1,380,000
fr fr
General Obligation Bonds go 5,000,000 go go
State s 11,670,000 s s
Operating Transfer - Other Funds to 200,000
to to
Total Sources of Funds 38,580,000 2,680,000 1,380,000
Unfunded Projects - - -
Total of NEW FUNDING requests 880,000
Total adjustments to prior years' funding authorizations
-
Total Cost 880,000
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
25,000 fr 25,000 fr 25,000 fr 25,000 fr 25,000 fr
5,000 fr 5,000 fr 5,000 fr 5,000 fr 5,000 fr
5,000 fr 5,000 fr 5,000 fr 5,000 fr 5,000 fr
75,000 fr 75,000 fr 75,000 fr 75,000 fr 75,000 fr
100,000 fr 100,000 fr 100,000 fr 100,000 fr 50,000 fr
25,000 fr 25,000 fr 25,000 fr 25,000 fr 25,000 fr
10,000 fr 10,000 fr 10,000 fr 10,000 fr 10,000 fr
200,000 fr 200,000 fr 200,000 fr 200,000 fr 200,000 fr
300,000 fr 300,000 fr 300,000 fr 300,000 fr 300,000 fr
40,000 fr 40,000 fr 40,000 fr 40,000 fr 40,000 fr
500,000 fr 300,000 fr
5,670,000 fr
11,670,000 s
5,000,000 go 200,000 to
850,000 fr
23,625,000 1,285,000 1,635,000 785,000 735,000
6,955,000 fr 1,085,000 fr 1,635,000 fr 785,000 fr 735,000 fr
5,000,000 go go go go go
11,670,000 s s s s s
200,000
to to to to to
23,625,000 1,285,000 1,635,000 785,000 735,000
- - - - -
785,000 785,000 785,000 785,000 735,000
-
- - - -
785,000 785,000 785,000 785,000
735,000
Destination Medical Center 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
Operations
8602 5,297,065 268,750 sd 247,000 sd
1 Contributions to DMC Corporation for DMCC expenses
32,198,639
8602 2,235,776 sd 2,190,000 sd
2 Contributions to DMC Corporation for EDA expenses
8,674,823
8601 696,215 sd 738,616 sd
3 City Project Management expenses
4 City of Rochester Administrative costs for DMC projects 1,800,000
8601 100,000 sd 100,000 sd
1,250,000
5 Development Plan Update
3,275,616
Public Realm
6 Chateau Theatre Improvements - Renovation of restrooms 2022 plus additional
improvements and HVAC upgrades 2023.
12,176,802
8624 350,000 sm
100,000 sd
7
Sales Tax DMC - Repayment of loan from Flood Control Reserves; 7 year repayment
8605 8,400,000 1,200,000 sd 1,200,000 sd
starting in 2018.
18,920,000
8904 7,000,000 sm
8 Discovery Walk Design and Implementation
7,000,000 sm
5,000,000
500,000 sm
9 Discovery Walk Phase 2 - Soldiers Field Park
Riverfront Reimagined 6,000,000
1,000,000 sm
10
19,871,265
8625
11 Heart of the City
6,000,000 sm 600,000 sm
Heart of the City Phase 2 - University Square to Mayo Civic Center 12,000,000
12
3,300,000
13 St Marys Place Public Realm Implementation
9,650,000
Strategic Redevelopment
Strategic Redevelopment 25,000,000 7,000,000 sm 3,000,000 sm
14 8633
3,000,000
Streets and Sewers
28,000,000 5,425,000 go 6,575,000 go
15 District Energy System Rochester
200,000 sm 1,800,000 sm
14,000,000 s
16 Block 6 Ramp - Roadway improvements, utility replacements, upgrades and relocations
for water and electric. Project reserves will be transferred from J2201. 789,000 sm
1,578,000
118,000 os
223,000 ow
206,000 wu
242,000 r
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
253,000 sd 259,000 sd 265,000 sd 272,000 sd 279,000 sd
2,244,750 sd 2,300,870 sd 2,358,390 sd 2,417,350 sd 2,477,780 sd
757,081 sd 776,008 sd 795,409 sd 815,294 sd 835,676 sd
100,000 sd 100,000 sd 100,000 sd 100,000 sd 100,000 sd
500,000 sm
3,354,831 3,435,878 4,018,799 3,604,644 3,692,456
1,000,000 sm 100,000 sm 100,000 sm 100,000 sm 100,000 sm
1,200,000 sd 1,200,000 sd
1,720,000 sm
4,500,000 sm
5,000,000 sm
1,200,000 sm 6,000,000 sm 4,800,000 sm
300,000 sm sm
3,000,000
13,720,000 5,500,000 6,100,000 4,900,000 100,000
3,000,000 sm 3,000,000 sm 3,000,000 sm 3,000,000 sm 3,000,000 sm
3,000,000 3,000,000 3,000,000 3,000,000 3,000,000
Destination Medical Center 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
17 Construct sanitary sewer capacity bypass on 3rd Ave SW from 2nd St SW to 4th St SW
3,100,000
18 South Broadway Reconstruct from 4th St SW to 9th St SW 21,000,000
Downtown Sidewalk Experience Enhancement (ADA Improvements, Increase Public
19
Realm Space & Aesthetic Integration). Tax abatement project reserves will be used for a
portion of this project.
2,950,000 848,375 sm 2,051,625 sm
50,000 r
20 Civic Center Drive Expansion 750,000
26,004,625
Mobility
21 Arrive Rochester Implementation 8709 1,650,000 60,000 sd 180,000 sd
8707 114,542,500 2,100,800 tc 4,155,534 tc
22 ITS Implementation: Rapid Transit (Includes 2nd Street Recon & Streetscape)
3,151,200 ts 10,388,836 ts
200,000 f 2,100,000 f
2,040,277 sm
8,000,000
1,600,000 sd sd
23 ITS Study Repayment 1,600,000
9,000,000
sd
24 ITS Implementation Phase II 200,000
20,664,647
Total Cost
350,459,094 39,236,116 62,594,888
Sources of Funds
Special Assessment Bonds a 750,000 a
Olmsted County c 250,000 c
Federal f 56,286,300 2,100,000
f
General Obligation Bonds go 12,000,000 6,575,000 go
Operating Transfer - fr Storm Water Utility os 330,500 118,000 os
Operating Transfer - fr Sewer Utility ow 2,210,500 223,000 ow
Private Funds p 500,000
p
Project reserves r 5,292,000 242,000 r
State s 14,000,000 14,000,000 s
Sales Tax DMC sd 72,698,454 6,455,616 sd
State DMC Funds sm 125,252,880 18,130,902
sm
Transit Aid County DMC tc 19,116,303 4,155,534 tc
Transit Aid State DMC ts 40,741,157 10,388,836 ts
Operating Transfer - Other Funds to 562,500 to
Water Utility wu 468,500 206,000
wu
Total Sources of Funds
350,459,094 62,594,888
- - -
Unfunded Projects
Total of NEW FUNDING requests 62,594,888
Total adjustments to prior years' funding authorizations
-
Total Cost 62,594,888
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
50,000 ow 1,500,000 ow
50,000 sm 1,500,000 sm
1,000,000 sm 15,000,000 sm
5,000,000 r
750,000 sm
100,000 3,000,000 1,000,000 20,000,000 750,000
180,000 sd 180,000 sd 180,000 sd 180,000 sd 180,000 sd
4,542,581 tc 3,368,588 tc
11,356,451 ts 8,421,470 ts
23,939,321 f 26,352,979 f 3,694,000 f
1,953,000 sm 1,780,463 sm
150,000 wu
225,000 ow
750,000 a
sd
1,600,000
sd
300,000
400,000 tc 3,000,000 tc
600,000 ts 4,500,000 ts
43,871,353 41,228,500 3,874,000 1,180,000 7,680,000
64,046,184 56,164,378 17,992,799 32,684,644 15,222,456
a 750,000 a a a
c c c c c
23,939,321 f 26,352,979 f 3,694,000 f f f
go go go go go
os os os os os
50,000 1,725,000
ow ow ow ow ow
p p p p p
5,000,000
r r r r r
s s s s s
6,634,831 sd 4,815,878 sd 3,698,799 sd 3,784,644 sd 3,872,456 sd
17,523,000 sm 10,580,463 sm 10,600,000 sm 22,900,000 sm 3,850,000 sm
4,542,581 tc 3,368,588 tc tc 400,000 tc 3,000,000 tc
11,356,451 ts 8,421,470 ts ts 600,000 ts 4,500,000 ts
to to to to to
150,000
wu wu wu wu wu
64,046,184 56,164,378 17,992,799 32,684,644 15,222,456
- - - - -
64,046,184 56,164,378 17,992,799 32,684,644 15,222,456
- - - - -
64,046,184 56,164,378 17,992,799 32,684,644 15,222,456
Downtown Development/Tax Abatement District 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Proj # Total Budget CIP Bdgt Amts 2022 Priority
Map # Project Description
1 Contribution to RDA to award and administer commercial rehabilitation grants. Funding
4,225,000
2602 125,000 r 2
to be provided by Tax Abatement Project Reserves.
2 Contribution to RDA for the Clean and Safe Program. Funding to be provided by Tax
Abatement project reserves.
500,000 125,000 r 125,000 r 1
Total Cost 4,725,000 125,000 250,000
Sources of Funds
Tax Abatements ad 3,350,000 ad ad
Project reserves r 1,375,000 125,000 250,000
r r
Total Sources of Funds 4,725,000 125,000 250,000
Unfunded Projects - - -
Total of NEW FUNDING requests 250,000
Total adjustments to prior years' funding authorizations
-
Total Cost 250,000
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
125,000 r 125,000 r 125,000 r 125,000 r 125,000 r
100,000 r
225,000 125,000 125,000 125,000 125,000
ad ad ad ad ad
225,000 125,000 125,000 125,000
r r r r 125,000 r
225,000 125,000 125,000 125,000 125,000
- - - - -
225,000 125,000 125,000 125,000 125,000
- - - - -
225,000 125,000 125,000 125,000 125,000
Fire Projects 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
Retained Earnings = re
GO Revenue Bonds = rb State Funds = s
Storm Water Mgmt Chg = sw
Sales Tax 2013 = st Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
1 Fire Station Infrastructure Improvements at various stations. Energy efficiency efforts,
LED installations, roof and other planned maintenance. Prior year reserves transferred
from J1918 (Misc. Fire Equipment-non vehicles).
1024 2,125,000 200,000 t 200,000 t 1
2 Emergency Management Improvements - This will be used for Siren / modular
replacement and new locations.
1924 362,910 45,000 t 10,000 t 2
3 Fire Records Software
1972 165,000 20,000 t 20,000 t 3
Emergency Operations Center (EOC) Technology - This will be used for updated
4
technology and modifications to the City EOC location.
2049 304,400 10,000 t 10,000 t 4
6 VHF Backup Radio Paging System 1960 60,000
7 Rochester Mesonet Weather Station 60,000
29,500 3,000 t
8 Emergency Management - tPt Now Rochester.
Total Cost 3,106,810 278,000 240,000
Sources of Funds
Federal f 63,750
f f
Project reserves r 212,910
r r
Tax Levy t 2,830,150 278,000 240,000
t t
Total Sources of Funds 3,106,810 278,000 240,000
Unfunded Projects - - -
Total of NEW FUNDING requests 240,000
Total adjustments to prior years' funding authorizations
-
Total Cost 240,000
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
200,000 t 250,000 t 200,000 t 200,000 t 250,000 t
45,000 t 10,000 t 45,000 t 10,000 t 45,000 t
20,000 t 20,000 t 20,000 t 20,000 t 25,000 t
20,000 t 20,000 t 20,000 t 20,000 t 25,000 t
10,000 t 10,000 t 10,000 t 15,000 t 15,000 t
7,500 t
22,500 f
1,500 t
326,500 310,000 295,000 265,000 360,000
22,500 f f f f f
r r r r r
304,000 310,000 295,000 265,000
t t t t 360,000 t
360,000
326,500 310,000 295,000 265,000
- - - - -
326,500 310,000 295,000 265,000 360,000
- - - - -
326,500 310,000 295,000 265,000 360,000
Police Projects 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
1 Public Safety camera system.
1891 268,000 24,000 t 30,000 t 1
3
North Station & Service Center - Interfund loan in 2017 from the Group Insurance Fund
for original purchase of site land & building.
1023 27,643,000 367,000 t 2
1,040,000 t
Total Cost 27,911,000 1,064,000 397,000
Sources of Funds
General Obligation Bonds go 735,000 go go
Project reserves r 576,428 r r
General Obligation Revenue Bonds rb 22,000,000 rb rb
Tax Levy t 4,182,572 1,064,000 t 397,000 t
Operating Transfer - Other Funds to 417,000
to to
Total Sources of Funds 27,911,000 1,064,000 397,000
Unfunded Projects - - -
Total of NEW FUNDING requests 397,000
Total adjustments to prior years' funding authorizations
-
Total Cost
397,000
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
30,000 t 30,000 t 30,000 t 30,000 t 30,000 t
367,000 t 367,000 t
397,000 397,000 30,000 30,000 30,000
go go go go go
r r r r r
rb rb rb rb rb
397,000 t 397,000 t 30,000 t 30,000 t 30,000 t
to to to to to
397,000 397,000 30,000 30,000 30,000
- - - - -
397,000 397,000 30,000 30,000 30,000
- - - -
-
30,000
397,000 397,000 30,000 30,000
Library Projects 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
1 Public Library technology hardware/software equipment replacement: To align with the
priorities in the Strategic Plan, which focuses on listening to and addressing the needs
of our diverse and growing community, the Library utilizes the J2041 fund to update
and replace end of life hardware, software, and networking infrastructure. Funds will be
transferred from the Library Information Technology Revolving Fund.
2041 13,604 c 14,284 c 1
2,802,680
117,384 to to 1
276,855
2 Rochester Public Building (RPL) building improvements involving projects to maintain
an existing City building and augment facility capabilities. Planned projects include LED
lighting upgrades; public furniture re-upholstery; replacement office chairs (many are
original to the building-1995); Sit to Stand units (purchase 3-5 units to meet the
ergonomic needs of team members); and finishing/painting/drywall repair etc. Funds
will be transferred from Library Reserves.
2039 1,823,480 23,000 to 23,000 to 2
35,600 c 35,600 c 2
Total Cost 4,626,160 189,588 349,739
Sources of Funds
Olmsted County c 799,234 49,204 49,884
c c
Local Government Aid ga 34,610 ga ga
Operating Transfer - fr General Fund ot 318,028 ot ot
Tax Levy t 808,538 t t
Operating Transfer - Other Funds to 2,665,750 140,384 299,855
to to
Total Sources of Funds 4,626,160 189,588 349,739
Unfunded Projects - - -
Total of NEW FUNDING requests 349,739
Total adjustments to prior years' funding authorizations
-
Total Cost 349,739
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
15,713 c 16,498 c 17,323 c 18,189 c 19,099 c
41,536 to 175,802 to 60,626 to 84,161 to 306,098 to
24,000 to 25,000 to 26,000 to 27,000 to 28,000 to
34,800 c 33,800 c 32,900 c 32,000 c 31,500 c
116,049 251,100 136,849 161,350 384,697
50,513 50,298 50,223 50,189 50,599
c c c c c
ga ga ga ga ga
ot ot ot ot ot
t t t t t
65,536 200,802 86,626 111,161 334,098
to to to to to
116,049 251,100 136,849 161,350 384,697
- - - - -
116,049 251,100 136,849 161,350 384,697
- - - - -
116,049 251,100 136,849 161,350 384,697
Administrative Projects 2022-2027 Capital Improvement Plan
Special Assessment Bonds = a Abatement District = ad Olmsted County = c
Flood Control Reserves = fr Local Gov't Aid = ga General Obligation Bonds = go
Operating Trfs-fr General Fund = ot Operating Trfs-fr Sewer Utility = ow Operating Trfs-fr General Fund = ox
GO Revenue Bonds = rb Retained Earnings = re State Funds = s
Sales Tax 2013 = st Storm Water Mgmt Chg = sw Tax Levy = t
Operating Trfs - fr Other Funds = to Transit Aid State DMC = ts Water Availability Chg = wa
2021
Map # Project Description Proj # Total Budget CIP Bdgt Amts 2022 Priority
125 Live Facility
1,158,000 193,000 t 1
1
City ERP System: The city ERP system faces upgrades every 2-4 years to maintain
2
support from the supplier. These upgrades require expert consulting services for
unique skills city resources don't have and project management services. This request
is to put aside funds on an annual basis to allow for these upgrades without putting the
full financial burden in any specific year.
1971 779,281 50,000 t 50,000 t 3
3 City Metropolitan Network: Primary role of this program is to enhance the city owned
fiber network across the city in support of city operations. We participate with RPU,
water, sewer, traffic operations, police, county, DOT and other state organizations to co-
locate/co-fund fiber installations whenever possible to reduce costs.
1998 25,000 t 50,000 t 4
1,512,833
City wide IT Security tooling: Continue to improve our security posture across all city IT
4
(City Hall, RPU, RPL) solutions to reduce the likelihood of virus, phishing, ransomware
and other IT security breaches. In 2020 and going forward we need to contract with a
3rd party service for penetration testing of high risk Internet facing and internal
solutions including PCI compliance, CJIS requirements, and data consider personal by
the state. This testing is needed to meet our security policies.
1895 600,000 17,500 t 2
4,500 eu 2
500 wu 2
1,250 to 2
1,000 ow 2
250 os 2
Implement Storage Area Network for City Video
150,000 150,000 t
6 5
7 Automated Time Entry System: Upgrade Kronos time keeping system to the latest
release and additional consulting services as needed.
The Kronos time scheduling and time keeping system is used by most City employees
as a feed into the payroll system. The complexity of our different pay structures
requires a top tier system to meet the needs of payroll efforts. This CIP has not had
funds added to it in many years as the original funding has been consumed for
previous upgrades and consulting as needed. The balance is now insufficient to fund
our next upgrade.
1961 75,000
8 City Hall Badge Readers - Replace end of life badge printer in 2023. 1911 95,000
Total Cost 4,370,114 75,000 468,000
Sources of Funds
Electric Utility eu 108,000 eu 4,500 eu
Operating Transfer - fr Storm Water Utility os 6,000 os 250 os
Operating Transfer - fr Sewer Utility ow 24,000 ow 1,000 ow
State s 150,000 s s
Tax Levy t 4,040,114 75,000 t 460,500 t
Operating Transfer - Other Funds to 30,000 to 1,250 to
Water Utility wu 12,000 500
wu wu
Total Sources of Funds 4,370,114 75,000 468,000
Unfunded Projects - - -
Total of NEW FUNDING requests 468,000
Total adjustments to prior years' funding authorizations -
Total Cost 468,000
Schedule for Six Year Period
Electric Utility = eu Federal Funds = f Food & Beverage Tax = fb
Lodging Tax = lt MN State Aid - Streets = ms Operating Trfs - fr Storm Water = os
Private Funds = p 2020 Parks Referendum = pr Project Reserves = r
Sn/Sewer Avail Chg = sa Sales Tax DMC = sd State DMC Funds = sm
Transit Aid County DMC = tc Traffic Improvement Dist Chg = td Tax Increments = ti
Water Utility = wu Unfunded = u
2023 Priority 2024 Priority 2025 Priority 2026 Priority 2027 Priority
193,000 t 193,000 t 193,000 t 193,000 t 193,000 t
50,000 t 50,000 t 50,000 t 50,000 t 50,000 t
50,000 t 25,000 t 25,000 t 25,000 t 25,000 t
17,500 t 17,500 t 17,500 t 17,500 t 17,500 t
4,500 eu 4,500 eu 4,500 eu 4,500 eu 4,500 eu
500 wu 500 wu 500 wu 500 wu 500 wu
1,250 to 1,250 to 1,250 to 1,250 to 1,250 to
1,000 ow 1,000 ow 1,000 ow 1,000 ow 1,000 ow
250 os 250 os 250 os 250 os 250 os
25,000 t 25,000 t
5,000 t 5,000 t t
348,000 293,000 293,000 318,000 298,000
4,500 eu 4,500 eu 4,500 eu 4,500 eu 4,500 eu
250 os 250 os 250 os 250 os 250 os
1,000 ow 1,000 ow 1,000 ow 1,000 ow 1,000 ow
s s s s s
340,500 t 285,500 t 285,500 t 310,500 t 290,500 t
1,250 to 1,250 to 1,250 to 1,250 to 1,250 to
500 500 500 500 500
wu wu wu wu wu
348,000 293,000 293,000 318,000 298,000
- - - - -
348,000 293,000 293,000 318,000 298,000
- - - - -
348,000 293,000 293,000 318,000 298,000