HomeMy WebLinkAboutDMCC Resolution No. 188-2025 (Authorizing Use of Unallocated Link BRT Project Contingency Funding)DESTINATION MEDICAL CENTER CORPORATION
RESOLUTION NO. 188-2025
A RESOLUTION AUTHORIZING USE OF UNALLOCATED LINK BRT PROJECT
CONTINGENCY FUNDING
The following Resolution was offered by Paul Williams, seconded by James Campbell.
BACKGROUND RECITALS
A. Pursuant to Resolution No. 156-2024, the Destination Medical Center Corporation
(the “DMCC”) approved general contingency funding (the “Contingency Funding”) for the Link
Bus Rapid Transit project and criteria for the preservation and use, approval, and reporting of the
Contingency Funding (the “Original BRT Contingency Criteria”).
B. Subsequently, the DMCC approved an increase in the Contingency Funding
pursuant to Resolution No. 174-2025 and approved revisions to the Original BRT Contingency
Criteria (the “BRT Contingency Criteria”) pursuant to Resolution No. 181-2025.
C. The Destination Medical Center Economic Development Agency (the “EDA”) and
the City of Rochester (the “City”) staff recommend authorization for the use of unallocated
Contingency Funding, pursuant to the BRT Contingency Criteria, in such amount and subject to
the requirements set forth in the change order request attached hereto as Exhibit A (the
“Contingency Funding Use Request”).
D. The Staff of the City and the EDA requests that the DMCC approve the
Contingency Funding Use Request.
RESOLUTION
NOW, THEREFORE, BE IT RESOLVED, by the DMCC Board of Directors, that the
DMCC approve the Contingency Funding Use Request based on the following conditions:
1. Use of the Contingency Funding shall be in strict compliance with all requirements
set forth in the BRT Contingency Criteria.
2. The scope of approval of the Contingency Funding Use Request is limited to that
set forth in the Contingency Funding Use Request attached hereto as Exhibit A.
3. Any modification to the Contingency Funding Use Request will be subject to
subsequent approval by the DMCC.
BE IT FURTHER RESOLVED, that the Chair or the Treasurer of the DMCC is
authorized and directed to transmit this Resolution to the City and to take such actions as are
necessary and appropriate to effectuate the findings and approvals of this Resolution.
41189380v1
The question was on the adoption of the Resolution and there were 8 YEAS
and 0 NAYS, as follows:
BOARD OF DIRECTORS
Destination Medical Center Corporation
YEA NAY OTHER
Douglas M. Baker, Jr. X
Kristin Beckmann X
James R. Campbell X
Kim Norton X
Randy Schubring X
Mark Thein X
Pamela Wheelock X
Paul D. Williams X
RESOLUTION ADOPTED on December 10, 2025.
ATTEST:
Pamela Wheelock, Chair
Destination Medical Center Corporation
EXHIBIT A
EXHIBIT A
November 12, 2025
TO: Destination Medical Center Corporation
From: Patrick Seeb, Executive Director, DMC Economic Development Agency
Cindy Steinhauser, Deputy Administrator, City of Rochester
RE: Approving Release of Unallocated Contingency Funding According to the
BRT Contingency Use Criteria
Request of the Board of Directors:
It is requested that the Board authorize the use of $975,000 from unallocated contingency within
the DMC County and State Aid Transit Funds and the Federal Transit Administration Small
Starts Grant, in accordance with the approved LINK BRT contingency use guidelines. Approval
of this change order will permit the contractor to proceed with construction activities under
winter work conditions, thereby improving the overall project schedule through modifications to
the construction means and methods for the Saint Mary’s Transit Center. This authorization will
help maintain project momentum and mitigate potential schedule delays and cost increases
associated with extended construction timelines.
Background:
The LINK BRT system is a transformative transportation investment designed to enhance
mobility, reduce congestion, and support the continued growth of Rochester. The Volume C –
Platforms and Tunnel contract was executed on July 21, 2025, in the amount of $75,339,925.
LINK BRT contractor Elcor Construction has been working for the past several months along
2nd Street SW in front of Saint Marys Hospital, completing utility and roadway construction. The
project is now at a stage where tunnel construction could proceed. A construction duration of
approximately 18 months is required to complete the Saint Marys Transit Center, however, two
constraints are preventing advancement. Work on the north vertical circulator is paused pending
the acquisition of additional temporary shoring and excavation easements. Work on the south
vertical circulator is paused due to a recently identified conflict requiring the relocation of high-
voltage underground electrical lines. For reference, the current schedule anticipates substantial
construction completion by June 17, 2027, revenue service commencement on August 19,
2027, and FTA grant closeout by March 19, 2028.
Change Order Justification:
The Contractor is now prepared to start work on the pedestrian tunnel. The following two
scenarios provided schedule options to advance the project.
Scenario 1: Continue construction according to current means and methods, no change
order authorization to modify means and methods or perform winter work. The following
are considerations for continuing under Scenario 1.
• Construction of the Saint Marys Transit Center would not begin until April 1, 2026. The
120-day delay in the start of work is due to the need to use the eminent domain process
to obtain the additional required temporary easements.
• This would push completion to October 1, 2027. System start-up and compliance testing
would also be delayed, with final commissioning and commencement of service not
occurring until November 1, 2027.
• The delayed service commencement would, in turn, postpone Final Project Closeout of
the FTA Grant to May 2028, requiring an amendment to extend the project schedule
under the Small Starts Grant Agreement with the Federal Transit Administration.
• Scenario 1 would also extend the closure of 2nd Street SW by approximately 16 weeks,
as both the north and south vertical circulators would need to be constructed
concurrently to minimize further schedule impacts.
• Performing construction on both the north and south vertical circulators concurrently
would interfere with work at the 2nd Street SW and 14th Avenue SW intersection, restrict
available traffic lanes, and negatively affect emergency room access from the east.
Scenario 2: Allow work on Saint Marys Transit Center to proceed immediately without
delay by authorizing a change order to fund winter work conditions ($350,000) and
modifications to construction means and methods ($625,000).
• The change order funding will be used to modify the earth shoring and retention system
by enabling multiple installation setups, eliminating the need for easements to construct
the north vertical circulator, and include provisions for heated and enclosed work areas
during winter.
• The contractor will maintaining one lane of traffic in each direction on 2nd Street SW and
keeping a pedestrian route open on the south side of the roadway throughout the winter
and will maintain at least one lane of traffic in one direction on 2nd Street SW at all
times, ensuring improved emergency room access from the east.
• In May 2026, additional temporary pavement will be placed over the newly completed
tunnel segment to shift vehicle and pedestrian routes to the north half of 2nd Street SW.
The contractor will then begin construction of the south vertical circulator building and
the southern half of the tunnel.
• The construction duration for the Saint Marys Transit Center under this scenario is 18
months, beginning December 1, 2025, and concluding June 1, 2026. This schedule
allows for system start-up and compliance testing to occur as originally planned,
maintaining the operational service date and supporting the Link BRT opening in Q2
2027.
The City believes proceeding with Scenario 2 is the best option to maintain the project’s overall
schedule, provide better access to the traveling public, and improve emergency room access
from the east and therefore is recommending approval of this change order. This would increase
the total project cost to approximately $176.1 million including previously approved change
orders.