RESOLUTION NO. 195-2026
A RESOLUTION APPROVING FINAL APPROVAL OF EXPENDITURE OF FUNDS
FOR PUBLIC INFRASTRUCTURE IMPROVEMENTS
The following Resolution was offered by Paul Williams, seconded by Mark Thein.
BACKGROUND RECITALS
A.In the 2026-2027 Five Year Capital Improvement Plan (the “2026-2027 CIP”)
approved by the Destination Medical Center Corporation (“DMCC”) on September 25, 2025 per
Resolution No. 178-2025, the DMCC approved the Downtown Public-Private Infrastructure
Investment Alignment project (the “Project”) in association with Mayo Clinic’s Bold. Forward.
Unbound in Rochester initiative (the “Approval”).
B.The Approval recognized that planning efforts for the Project were in a preliminary
stage and that such planning efforts would shape the project scope and funding needs. Given this,
the Approval was conditioned upon the requirement that further detail and information as to public
realm and infrastructure plans and proposed findings be presented to the DMCC for specific
approval of the project plan and costs prior to proceeding with construction.
C.A portion of the Project, specifically construction of the Utility Power Underground
Infrastructure Package B3 (the “UPUI”), as further detailed on Exhibit A, is ready to advance to
construction pending further authorization by the DMCC to expend up to $3,600,000 from the
Approval for construction of the UPUI (the “UPUI Project”).
D.Staff of the City of Rochester (“City”) and the Destination Medical Center
Economic Development Agency (“EDA”) now request that the DMCC approve authorization of
the UPUI Project.
RESOLUTION
NOW, THEREFORE, BE IT RESOLVED, by the DMCC Board of Directors, that the
DMCC approves the UPUI Project and that the DMCC hereby approves the UPUI Project as a
public infrastructure project within the meaning of Minnesota Statutes Section 469.40,
Subdivision 11, and consistent with the Development Plan, adopted on April 23, 2015, as
amended; provided that:
1.The scope of approval for the UPUI Project is set forth in the attached Exhibit A;
2.Any material deviation from the scope of approval for the UPUI Project will be
subject to subsequent approval by the DMCC, which approval shall be based upon review and
final determination of scope, costs, and availability of funds; and
3.The EDA and City are directed to provide the DMCC Board of Directors with
regular updates with respect to the scope and costs of the UPUI Project.
2
BE IT FURTHER RESOLVED, that the Chair and Treasurer are hereby authorized and
directed to transmit this Resolution to the City and to take such actions as are necessary or
convenient to effectuate this Resolution.
42821960v2
The question was on the adoption of the Resolution and there were 7 YEAS
and 0 NAYS, as follows:
BOARD OF DIRECTORS
Destination Medical Center Corporation
YEA NAY OTHER
Douglas M. Baker, Jr. X
Kristin Beckmann X
Kim Norpton X
Randy Schubring X
Mark Thein X
Pamela Wheelock X
Paul D. Williams X
RESOLUTION ADOPTED on May 21, 2026.
ATTEST:
Pamela Wheelock, Chair
Destination Medical Center Corporation
EXHIBIT A
DOWNTOWN INFRASTRUCTURE ALIGNMENT
MAY 2026
TO: DMC CORPORATION BOARD OF DIRECTORS
FROM: DMC ECONOMIC DEVELOPMENT AGENCY
Request of the Board
Authorize expenditure of up to $3.6 million from the Downtown Infrastructure Alignment
program for construction of Utility Power Underground Infrastructure (UPUI) Package
B3.
The project is being advanced pursuant to the downtown infrastructure plan and
includes: upgrades to sanitary sewer, stormwater, and water infrastructure; street and
streetscape reconstruction; completion of remaining utility grades and street
improvements not impacted by Mayo Clinic’s separate UPUI B3 Package; and
coordination with Mayo Clinic to align construction schedules and minimize community
impacts.
The project will be funded from the approved 2026–2027 DMC CIP, which includes
$38,371,000 for Downtown Public-Private Infrastructure Investment Alignment.
Why Board Attention Is Needed Now
The City of Rochester and DMC EDA are moving from program-level planning into
project-by-project implementation within the geography affected by Bold. Forward.
Unbound. in Rochester. The approved 2026 CIP anticipated that this work would require
active coordination of public and private infrastructure to achieve “maximum public
benefit with minimum public impact.”
That coordination is now especially important because Mayo Clinic’s utility and campus-
expansion work is moving quickly and is already shaping the sequencing of adjacent
public infrastructure. The City and Mayo Clinic have entered, or are preparing, a series
of coordination, development, and infrastructure agreements addressing utility plant and
underground infrastructure, roadway replacement, stormwater management, site
development, and future civil infrastructure work in the public right-of-way.
In the near term, some public infrastructure packages must be advanced on an
accelerated basis to stay aligned with adjacent institutional work. Following these initial,
time-sensitive projects, staff intend to provide the board with a more consistent and
foreseeable approval cadence, including visibility into upcoming construction packages,
major dependencies, and anticipated funding requests.
This funding authorization follows the City of Rochester’s expenditure of up to $400,000
for necessary project design under the approved 2026 Capital Improvement Plan (CIP)
and would allow the project to advance from design into construction in coordination
with adjacent downtown infrastructure work.
Approved Project or Program Baseline
The approved 2026–2027 DMC CIP includes $38,371,000 for Downtown Public-Private
Infrastructure Investment Alignment, approximately $19,185,500 per year. The project
supports street, water, storm sewer, public realm, and sanitary sewer improvements in
the geography impacted by Bold. Forward. Unbound. in Rochester.
When the board approved the 2026–2027 CIP, it specifically recognized that planning
efforts for this set of projects were at a preliminary stage and would shape project scope
and funding needs over time. The board further provided that more detailed public realm
and infrastructure plans, along with proposed funding, would return to the DMCC for
specific approval, while allowing the City to expend a portion of project funds on
necessary design and planning in the interim.
The attached Original Funding Matrix substantially defines that approved program
baseline. It identifies the corridor and block segments within the impacted geography
and distinguishes between Mayo Clinic and City responsibilities (including DMC-funded
projects). The overall program is expected to conclude construction in 2029
Current Status
Downtown Infrastructure Alignment is in early implementation. Staff have identified the
blocks affected by BFUIR-related work, grouped them into logical project packages for
delivery, assigned project managers, and developed preliminary schedules. Kickoff work
has occurred, monthly coordination meetings are underway, and individual project
meetings are beginning as packages enter active design and delivery.
Several related projects are already advancing. The broader downtown infrastructure
effort includes projects already approved separately from the $38.371 million program,
as well as packages that will return to the board as scope, timing, and cost become
sufficiently defined. The overall project is expected to proceed by phased, specific
approvals rather than through a single blanket release of the entire project budget. The
attached “Current and Planned Project Area” map illustrates these projects.
As these projects intersect, the development of the public realm including streets,
sidewalks, public and private spaces, and the infrastructure that supports utilities,
transportation, wayfinding, and comfort elements such as weather protection and
seating must be considered not as isolated segments but as an interconnected system.
A Request for Qualifications has been issued to develop a public realm plan. This plan
will include a framework and strategy to guide the design and implementation of these
projects.
Risks to Scope, Budget, Timeline, or Delivery
• Sequencing interdependency on related Mayo Clinic work. Shifts in schedule or
field conditions may require public infrastructure work to be re-sequenced.
• Compressed implementation timing. Some public improvements are being planned
and delivered in a context Mayo Clinic work is underway or imminent, creating
pressure to move design, approvals, and construction packaging quickly enough to
avoid lost windows, rework, or avoidable disruption.
• Continued budget refinement. The 2026 DMC CIP establishes the program
budget, and the funding matrix identifies a recommended allocation framework,
and individual package costs will continue to mature as design progresses,
estimates are refined, and bids are received. Early budgets were prepared to
reflect a variety of considerations which can impact costs over time, including
construction contingencies and cost escalations related to expected changes in
the labor market.
• Downtown access and coordination complexity. Multiple overlapping projects in a
constrained urban environment require careful phasing, closure management,
business access planning, and communication. The shared City/Mayo/DMC
principles expressly commit the partners to optimizing schedules, managing road
closures, applying the Business Forward model, improving connectivity, and
maintaining timely, actionable communications.
Upcoming Requests or Decision Points
Staff expect additional project-specific design and construction authorizations to come
forward as scopes mature and construction schedules are confirmed. Going forward,
staff will provide the board with a rolling outlook showing:
• the next packages expected for funding authorization (see “Schedule of
Projects”)
• major City or Mayo Clinic dependencies
• and any foreseeable scope, budget, or schedule revisions
DMC Alignment
Downtown Infrastructure Alignment reflects a core DMC responsibility: ensuring that
major private investment in Rochester is matched by public infrastructure that converts
that investment into broader and longer-lasting community value. The approved 2026–
2027 CIP expressly frames this program as a coordinated response to Mayo Clinic’s
transformative Bold. Forward. Unbound. in Rochester investment, intended to deliver
“maximum public benefit with minimum public impact” across the downtown.
In that sense, this approximately $38 million investment is not merely reactive
infrastructure work. It is part of the public-sector work required to shape Rochester’s
next phase of growth. As Mayo Clinic’s expansion strengthens Rochester’s role as
America’s City for Health, the surrounding infrastructure must also function at that level.
This investment helps ensure that growth is not simply accommodated, but intentionally
organized: in ways that improve connectivity, reduce repeated disruption, support future
development, and best protect the experience of patients, visitors, workers, residents,
and businesses during a period of major change. That is consistent with the shared
City/Mayo/DMC principles calling for aligned schedules, “dig once” infrastructure
investment, improved connectivity, Business Forward construction management, and
coordinated communications.
It also aligns with DMC’s broader emphasis on purposeful growth and designing for
well-being. Public infrastructure in this setting is not just a technical necessity. It shapes
whether downtown remains navigable, safe, legible, accessible, and economically
resilient while major institutional growth is occurring around it. By coordinating public
and private investment at this scale, DMC helps ensure that Rochester’s physical
environment supports not only Mayo’s expansion, but also the broader civic, economic,
and human experience that should accompany a leading health-focused city.
Attachments / Exhibits
• Schedule of Projects
• Original Funding Matrix
• Current and Planned Project Areas
Original Funding Matrix
Color code: Blue = Mayo Responsibility, Orange = Approved improvement already funded, Yellow = Option 1, Green = Option 2, Purple = Option 3
Map
Number
Location
Condition description Traffic Study or Site
Replacement standard
Estimate
1
Intersection at 6th Ave NW & Civic
Center Dr
Needs intersection improvements
for additional traffic demand No typology than standard
road $ 750,000
2
6th Ave NW between 4th St. NW &
Civic Center Dr above grade infrastructure only and
bike enhancements
No typology than standard
road $ 1,500,000
3
6th Ave NW between 3rd & 4th St.
NW infrastructure upgrades needed
(Sanitary 1945, Water 1936)
No typology than standard
$ 1,500,000
4
6th Ave NW between 2nd & 3rd St.
NW infrastructure upgrades needed
(Sanitary 1945, Water 1936)
No typology than standard
road $ 1,500,000
6th Ave NW between 1st & 2nd St.
NW infrastructure upgrades needed
(Sanitary 1945, Water 1936)
UPUI B3 & Site Plan
(50% of block) typology than standard
6th Ave NW between Center St W &
1st St NW infrastructure upgrades needed
(Sanitary 1945, Water 1936)
UPUI B3 & Site Plan typology than standard
Intersection of 6th Ave NW & Center
Street W
infrastructure upgrades needed
(Sanitary 1952, Stormwater 1984 & UPUI B3 & Site Plan Major roadway, greater
typology than standard
6th Ave NW between 1st St SW &
Center Street W
infrastructure upgrades needed
(Sanitary 1945 & 1952, Stormwater Site Plan Major roadway, greater
typology than standard
9
6th Ave NW between 2nd St. SW &
1st SW
infrastructure upgrades needed
(Sanitary 1945 & 1952, Stormwater
1946 & 1980, Water 1936 & 2014)
Site Plan Major roadway, greater
typology than standard
road $ 1,000,000
10
5th Ave NW between 3rd & 4th St NW Infrastructure to support future
demand (Sanitary 1945, water 1887) No increased capacity for
development $ 750,000
11
5th Ave NW between 2nd & 3rd St
NW
Infrastructure to support future
demand (Sanitary 1945, water 1887) UPUI B3 increased capacity for
development $ 750,000
12
5th Ave NW between 1st & 2nd St
NW
Infrastructure to support future
demand (Sanitary 1945, water 1887) UPUI B3 & Site Plan increased capacity for
development $ 750,000
Funding request Opt
1
Funding request Opt
2 - Recommended
Funding request
Opt 3
$ 750,000 $ 750,000
$ 1,500,000 $ 1,500,000
$ 1,500,000 $ 1,500,000
$ 1,500,000 $ 1,500,000
$ 750,000 $ 750,000
$ 750,000 $ 750,000 $ 750,000
$ 750,000 $ 750,000 $ 750,000
Original Funding Matrix
13
5th Ave NW between Center St W &
1st St NW demand (Sanitary 1945, Storm water
1946, water 1887)
UPUI B2 increased capacity for
development $ 500,000
14
4th Ave NW between 3rd St NW &
Civic Center Dr
infrastructure upgrades needed
(Sanitary 1945, Stormwater 1980,
Water 1928)
No Major roadway, greater
typology than standard
road $ 1,000,000
15
4th Ave NW between 2nd & 3rd St
NW infrastructure upgrades needed
(Sanitary 1945, Water 1928)
No typology than standard
road $ 1,000,000
16
4th Ave NW between 1st & 2nd St
NW infrastructure upgrades needed
(Sanitary 1945, Stormwater 1986)
No typology than standard
$ 1,000,000
17
4th Ave NW between Center St W &
1st St NW infrastructure upgrades needed
(Sanitary 1945, Stormwater 1986)
UPUI B3 & Site Plan typology than standard
road $ 1,000,000
4th Ave NW between Center St W &
1st St SW
infrastructure upgrades needed
(Sanitary 1945 & 2024, Stormwater Civil Pkg & Site Plan
4th Ave NW between 1st St SW & 2nd
St SW
infrastructure upgrades needed
(Sanitary 1985, Stormwater 1985 & Civil Pkg & Site Plan
4th Ave SW between 2nd & 3rd St SW demand (1/2 block small Stormwater No increased capacity for
3rd Ave NW between 3rd St NW &
Civic Center Dr small Sanitary line improvement No typology than standard
3rd Ave NW between 2nd & 3rd St
NW small Sanitary line improvement No typology than standard
23
3rd Ave NW between 1st & 2nd St
NW
infrastructure upgrades needed
(Sanitary 1984,Stormwater 1962,
Water 1984)
Civil Pkg D Major roadway, greater
typology than standard
road $ 1,000,000
24
3rd Ave NW between Center St W &
1st St NW
infrastructure upgrades needed
(Sanitary 1986,Stormwater 1963
&1971, Water 1986)
Civil Pkg D Major roadway, greater
typology than standard
road $ 1,000,000
25
Intersection of 3rd Ave SW & Center
St. W
infrastructure upgrades needed
(Sanitary 1945, Stormwater 1971, Site plan Major roadway, greater
typology than standard
road
$ 1,000,000 $ 1,000,000
$ 1,000,000 $ 1,000,000
$ 1,000,000 $ 1,000,000
$ 1,000,000 $ 1,000,000 $ 1,000,000
$ 1,000,000 $ 1,000,000 $ 1,000,000
$ 1,000,000 $ 1,000,000
Original Funding Matrix
26
3rd Ave SW from 1st SW to Center St.
W
infrastructure upgrades needed
(Sanitary 1945 & 1971, Stormwater
1971, Water 1986)
Civil Pkg & Site Plan Major roadway, greater
typology than standard
road
27
3rd Ave SW from 2nd St SW to 1st SW infrastructure upgrades needed
(Sanitary 1954, Stormwater 1954,
Water 2004)
Civil Pkg & Site Plan Major roadway, greater
typology than standard
road
28
2nd Ave NW between 2nd St NW &
Civic Center Dr demand (Sanitary 1945, Stormwater
1943, water 1916)
Civil Pkg increased capacity for
development $ 750,000
2nd Ave SW between 1st St SW &
Center St W
Infrastructure to support future
demand (Sanitary 1952, Stormwater
1946, water 1999)
No increased capacity for
development, no need to
2nd Ave SW between 1st SW and 2nd
St SW demand (Sanitary 1952, Stormwater Site Plan
1st Ave NW between 3rd St NW &
Civic Center Dr
improvement and infrastructure for
future demand (small Stormwater Traffic study Major roadway, greater
typology than standard
1st Ave NW between between 2nd &
3rd St NW
improvement and infrastructure for
future demand (small Stormwater Traffic study Major roadway, greater
typology than standard
1st Ave NW between 1st & 2nd St NW
ground improvements (Sanitary
2022, Minor storm replacement,
Water replacement & upsizing has
Traffic study
Major roadway, greater
typology than standard
road, undersized water
34
1st Ave NW between Center St W &
1st St NW improvements only (Water 2022),
minor storm and roadway only
Traffic study typology than standard
road $ 750,000
35
Intersection at 1st Ave NW & Center
St W for future demand (Sanitary sewer
1946)
Traffic study typology than standard
road $ 500,000
36
1st Ave SW between 2nd & 3rd St.
SW
Enhanced corridor and infrastructure
for future demand (Sanitary sewer
1948, water 1989 upsize to 12")
No Major roadway, greater
typology than standard
road $ 1,500,000
$ 750,000 $ 750,000 $ 750,000
$ 750,000
$ 500,000
$ 1,500,000
Original Funding Matrix
37
1st Ave SW between 3rd & 4th St. SW
Enhanced corridor and infrastructure
for future demand (Sanitary sewer
1948, stormwater 1948, water 1919
3 sections and upsizing)
No Major roadway, greater
typology than standard
road $ 1,500,000
38
3rd St NW between 5th & 6th Ave NW
Infrastructure to support future
demand (Sanitary 1945, Stormwater
1945, water 1887 upsizing)
No Regular standard with
increased capacity for
development $ 750,000
39
3rd St NW between 4th & 5th Ave NW demand (Sanitary 1945, water 1887
upsizing)
UPUI B3 increased capacity for
development $ 750,000
3rd St NW between 3rd & 4th Ave NW
Infrastructure to support future
demand (Sanitary 1945, Stormwater
1996 & 2001, water 1887 upsizing)
UPUI B3 Regular standard with
increased capacity for
development
3rd St NW between 3rd Ave NW &
Civic Center Drive
Infrastructure to support future
demand (Sanitary 1945, water
upsizing 1999)
No
3rd St NW between 2nd & 3rd Ave
NW
demand (Sanitary 1945, Stormwater
1945, water 1887 ) Mayo doing some UPUI B3 Regular standard with
increased capacity for
2nd St NW between 5th & 6th Ave
NW
Infrastructure to support future
demand (Sanitary 1947, Stormwater
1945, water 1887 need upsizing)
UPUI B3 Regular standard with
increased capacity for
2nd St NW between 2nd & 3rd Ave
NW
Infrastructure to support future
demand (Sanitary 1984, Stormwater
1945 & 1983, Water 1999 & 2011)
Civil pkg Regular standard with
increased capacity for
44
1st St NW between 5th Ave NW & 6th
Ave NW
demand, street is bituminous
pavement (water 1990 no
replacement 12")
UPUI & Site Plan Regular standard with
increased capacity for
development $ 750,000
1st St NW between 4th Ave NE & 5th
Ave NW demand, street is bituminous UPUI & Site Plan increased capacity for
45b
1st St NW between 3rd Ave NW &4th
Ave NE demand, street is bituminous
pavement (water 1986, storm)
Civil & Site Plan increased capacity for
development $ 750,000
$ 1,500,000
$ 750,000 $ 750,000
$ 750,000 $ 750,000 $ 750,000
$ 750,000 $ 750,000 $ 750,000
$ 750,000 $ 750,000 $ 750,000
Original Funding Matrix
46
Center St W between 5th & 6th Ave
NW
Cycle track & Infrastructure to
support future demand (Sanitary
2003, Stormwater 1984, Water 2003)
Traffic study Regular standard with
increased capacity for
Center St W between 4th & 5th Ave
NW
Cycle track & Infrastructure to
support future demand (Sanitary
2003, Stormwater 1984, Water 2003)
Traffic study Regular standard with
increased capacity for
48
Center St W between 3rd & 4th Ave
NW
support future demand (Sanitary
2003, Stormwater 1971 & 1986,
Water 2003)
Civil Pkg &Traffic
study
Regular standard with
increased capacity for
development
49
Center St W between 2nd & 3rd Ave
NW
Cycle track & Infrastructure to
support future demand (Stormwater
1971 & 1986, Water 1986 & 2000)
Civil Pkg &Traffic
study
Regular standard with
increased capacity for
development
Center St W between 1st & 2nd Ave
NW
ground improvements some
infrastructure for future demand
(Sanitary sewer 1963, Stormwater
1954, water 1963 cast iron
Traffic study Regular standard with
increased capacity for
1st St SW between 5th& 6th Ave NW -
North side only
Enhanced corridor primarily above
ground improvements some
infrastructure for future demand
(Sanitary sewer 1985 - Mayo,
Site plan & Civil
package B Major roadway, greater
typology than standard
52
1st St SW between 4th & 5th Ave NW -
North side only
Enhanced corridor primarily above
ground improvements some
infrastructure for future demand
Site plan & Civil
package B
Major roadway, greater
typology than standard
road $ 750,000
2nd St SW between 1st Ave SW & 6th
Ave SW
Mayo improvements
St. NW and 5th St. NW from 2nd Ave
NW to 4th Ave NW
demand (Sanitary 1945 & 1954 water Civil pkg
Kutzky park allocation $ 3,000,000 $ 8,000,000 $ 8,000,000
Revised total
$ 2,871,000 $ 2,871,000 $ 2,871,000
4
AV
E
NW
Current and Planned Project Areas
5 ST NW
1 A
2
2 ST NW
3
3 ST NW
4
10
38 39
11
42
14
21
40A
15
PUP
Expansion
40 Oct. '27
28
22
43
Central
Park
2 ST NW
5 12 16 23
1 ST NW
W CENTER ST
44
West
Logistics 6 (Feb. '29)
7
West
45A
North
Arrival
(P1 - Oct. '26
P2 - Apr. '27)
47
45B
17 24
1 ST NW
W CENTER ST
1 ST SW
Facilities
(Aug. '26) 8
9
51 52
Ozmun
(2029-2030)
29 Waterman
(2029-2030)
0 175 350
Feet
2025 Start
J7858 - 2nd Ave SW
2026 Start
J7857 - North Arrival ROW
2 ST SW
South
Parking 20
(Nov. '26)
2027 Start Date Exported: 2/24/2026
J8910 - 4th Ave between 2nd St & 3rd St
H - 3rd & 4th Aves from W Center St to Civic Center Dr
I - Mayo Package D & DMC Sanitary Sewer Upsizing
J8908 - 6th Ave & Connected UPUI
J8915 - Utility Power Underground
Infrastructure (UPUI) Package B3
2028 Start
D - 1st St SW to 4th Ave Tie-In
7
AV
E
NW
6
AV
E
SW
5
AV
E
SW
4
AV
E
SW
3
AV
E
SW
2
AV
E
SW
1
AV
E
NW
1
Schedule of Projects
DMC Board Meeting
Design (Funds are released and no further approval is needed.) 05/21/26 09/24/26 12/10/26 Q3 2027 Q4 2027 Q3 2028 Q4 2028 Total
Total Estimated Design Cost
DMC Board Meeting
Construction (DMC approval is required before release of funds.) 05/21/26 09/24/26 12/10/26 Q3 2027 Q4 2027 Q3 2028 Q4 2028
Total Estimated Construction Cost
Total