HomeMy WebLinkAboutDMCC Resolution No. 196-2026 (Revoking Approval of The Saint Marys Place Subdistrict Public Realm Plan, Reallocating Funds, and Amending the 2026-2027 Five Year Capital Improvement Plan to Provide for Near Term Improvements and Technical Analysis)DESTINATION MEDICAL CENTER CORPORATION
RESOLUTION NO. 196-2026
A RESOLUTION REVOKING APPROVAL OF THE SAINT MARYS PLACE
SUBDISTRICT PUBLIC REALM PLAN, REALLOCATING FUNDS, AND AMENDING
THE 2026-2027 FIVE YEAR CAPITAL IMPROVEMENT PLAN TO PROVIDE FOR
NEAR TERM IMPROVEMENTS AND TECHNICAL ANALYSIS
The following Resolution was offered by Kristin Beckmann, seconded by Paul Williams.
BACKGROUND RECITALS
A.The Development Plan was adopted by the Destination Medical Center Corporation
(“DMCC”) on April 23, 2015, as amended (the “Development Plan”), and includes the “Heart of
the City” as a subdistrict.
B.In 2021, construction was substantially completed on Peace Plaza and First Avenue
Southwest. This public realm project entailed renovating the eastern elements of the plaza and
surrounding areas, including universal design elements, sustainability features, integrated art and
improved infrastructure, and a catenary lighting system.
C.Pursuant to Resolution No. 141-2023, on September 28, 2023, the DMCC adopted
the 2024 Five Year Capital Improvement Plan (the “2024 CIP”).
D.The 2024 CIP included an approval of $500,000.00 in funding for the
implementation of a Saint Marys Place subdistrict public realm plan (the “Saint Marys Project”).
E.The Saint Marys Project will not proceed to implementation, and the DMCC hereby
determines that it is in the best interests of the DMCC to de-authorize the Saint Marys Project and
rescind the prior approval thereof.
F.The DMCC desires to reallocate $334,000.00 of the $500,000.00 originally
approved for the Saint Marys Project in the 2024 CIP to the 2026-2027 CIP to fund other capital
projects.
G.Pursuant to Resolution No. 164-2025, the DMCC approved the request from the
DMC EDA to increase the 2025 CIP in the amount of $175,000 to fund increasing the amount of
smooth pavers in East Peace Plaza and provide additional technical analysis of the Heart of the
City area.
H.The DMCC adopted the 2026-2027 Five Year Capital Improvement Plan (the
“2026-2027 CIP”) on September 25, 2025 per Resolution No. 178-2025.
I.Since completion of the construction of Peace Plaza, and the additional
authorization pursuant to Resolution No. 164-2025, the Destination Medical Center Economic
Development Agency (“EDA”) has continued to review the design of certain components of Peace
Plaza and has given consideration to improvements that would create a more equitable experience
within the plaza, as further detailed in the attached Exhibit A, not included within the 2026-2027
CIP (the “Capital Project”).
2
J.The EDA requests that the DMCC amend the 2026-2027 CIP to incorporate the
reallocation of $500,000.00 from the 2024 CIP, to add the Capital Project to the 2026-2027 CIP,
and to allocate $334,000.00 of the $500,000.00 to the Capital Project.
RESOLUTION
NOW, THEREFORE, BE IT RESOLVED, by the DMCC Board of Directors, that the
prior approval of the Saint Marys Project as set forth in the 2024 CIP and Resolution No. 141-
2023 is hereby de-authorized and rescinded, and the $500,000.00 originally approved for the Saint
Marys Project is hereby reallocated from the 2024 CIP to the 2026-2027 CIP to fund other capital
projects as approved by the DMCC.
BE IT FURTHER RESOLVED, that the DMCC approves an amendment to the 2026-
2027 CIP to incorporate the addition of the Capital Project and to allocate $334,000.00 from the
$500,000.00 originally approved for the Saint Marys Project under the 2024 CIP to the Capital
Project, and that the DMCC hereby approves the Capital Project as a public infrastructure project
within the meaning of Minnesota Statutes Section 469.40, Subdivision 11, and consistent with the
Development Plan; provided that:
1.The scope of approval for the Capital Project is set forth in the attached Exhibit A;
2.Any material deviation from the scope of approval for the Capital Project will be
subject to subsequent approval by the DMCC, which approval shall be based upon final
determination and review of scope, costs, and availability of funds; and
3.The EDA and City are directed to provide the DMCC Board of Directors with
regular updates with respect to the scope and costs of the Capital Project.
BE IT FURTHER RESOLVED, that the Chair and Treasurer are hereby authorized and
directed to transmit this Resolution to the City and to take such actions as are necessary or
convenient to effectuate this amendment to the 2026-2027 CIP.
42813114v3
The question was on the adoption of the Resolution and there were 5 YEAS
and 2 NAYS, as follows:
BOARD OF DIRECTORS
Destination Medical Center Corporation
YEA NAY OTHER
Douglas M. Baker, Jr. X
Kristin Beckmann X
Kim Norton X
Randy Schubring X
Mark Thein X
Pamela Wheelock X
Paul D. Williams X
RESOLUTION ADOPTED on May 21, 2026.
ATTEST:
Pamela Wheelock, Chair
Destination Medical Center Corporation
EXHIBIT A
HEART OF THE CITY
MAY 2026
TO: DMC CORPORATION BOARD OF DIRECTORS
FROM: DMC ECONOMIC DEVELOPMENT AGENCY
Request of the Board
Adopt the recommended amendment of the 2026-2027 DMC Capital Improvement Plan
(CIP) to provide up to $334,000 in DMC General State Infrastructure Aid (GSIA) to
support near-term improvements to the 1st Avenue SW pedestrian experience along
with undertaking additional technical analysis and a subgrade assessment of the Heart
of the City project limits. If approved, the funding required for this expenditure would be
reallocated from the $500,000 funding previously allocated to Saint Marys Place public
realm planning and implementation.
In February 2025 the DMCC Board of Directors approved $175,000 in funding to
support increasing the amount of smooth pavers in East Peace Plaza and additional
technical analysis of the Heart of the City area.
This funding request addresses recommended next steps based on results of the now
complete engineering design and construction work. If approved, DMC funding will be
used to execute two simultaneous streams of work:
• Improve the subsurface foundations and reset the pavers immediately adjacent to 64
tree wells along 1st Avenue between W. Center Street and 2nd Street SW. This
proposed work will include excavating the tree wells, pouring concrete to raise the
height of the tree well walls and installing a horizontal steel plate to provide more
durable support of the pavers immediately surrounding the tree well. This improved
design has been piloted for over a year, and no noticeable settlement has occurred
since its installation. This work will be completed as soon as bid documents can be
created and competitive bids can be solicited. Construction work is scheduled to
commence in mid-summer 2026.
• Conduct subgrade assessments through physical testing measures to identify
sources of soil material loss ultimately resulting in further paver settlement. Testing
and engineering measures will be used to inspect for offset pipe joints that may be
contributing to continued paver settlement in isolated spots and to look for leaks in
the Heart of the City hydronic snow melt system that is allowing glycol to escape
from the snowmelt piping network. Release of snowmelt system liquids can saturate
subsoils and become the cause of isolated paver settlement. This proposed work is
expected to be completed during late summer 2026 and would inform any future
capital improvements considered by the DMCC and Rochester City Council.
Approved Project or Program Baseline
The Heart of the City initiative represents a key component of the DMC public realm
development program, focused on transforming Peace Plaza and the 1st Avenue
corridor into a welcoming civic and commercial space. Originally identified in the 2015
DMC Development Plan and approved by the DMCC Board that year as a priority
capital project, the City of Rochester was designated as the implementing entity.
Funding commitments were incorporated into the 2016 and 2017 City Capital
Improvement Plans, enabling design development and early preconstruction work.
Construction began in 2019 after final design approval and funding authorization from
the DMCC Board, with substantial completion achieved in 2021.
The project included full reconstruction of East Peace Plaza, 1st Avenue streetscape
enhancements, public art installations, upgraded utilities, and improved stormwater
management. Following three years of heavy year-round use, a proactive maintenance
assessment identified localized paver settling and joint deterioration in East Peace
Plaza. To maintain long-term accessibility and durability, the DMC EDA and City
recommended, and the DMCC Board approved, a $175,000 project budget amendment
to support targeted paver resetting and surface smoothing treatment work in 2025.
During the summer of 2025 East Peace Plaza underwent modifications to enlarge and
improve the walking surface experience for those with impaired mobility and create a
more welcoming environment for all users of the space. Specifically, some of the pavers
with raised letters were removed and flat surfaced pavers were reinstalled along with
adding tree grates to the tree wells in East Peace Plaza. City staff worked with artist
Anne Hamilton who created the “A Song for Water” artwork on the plaza pavers. In
working with Ann, each row of pavers was analyzed before converting pavers with
words into smooth surface pavers to ensure the core meaning of the artwork’s poem
remained intact. The City conduct community member interviews after smooth surface
paver installation.
Through the modifications to the paver surface and adjustments to the tree wells around
the water feature, the City has enhanced the plaza’s environment to provide more
confidence for those with impaired mobility to utilize the space when it is activated while
also widen the ADA pedestrian access route which improves ease of navigating during
hosted events hosted in the plaza.
Current Status
City of Rochester staff have continued to evaluate the functionality and pedestrian
experience within Heart of the City. The tree well foundations along 1st Avenue have
been slowly settling since their initial installation. This has resulted in creating an
undesirable paver surface adjacent to the tree wells that is becoming a slowly growing
trip hazard.
In early 2025 one revised tree well design was installed and has been monitored for the
past 12 months and has shown no new paver settlement since installation. In addition,
for the past several winter seasons the hydronic snow melt system has needed a
measurable volume of fluid upon winter start up each fall. It is clear that the system is
leaking and city staff are proposing to undertake non-destructive testing to identify the
leak location(s) so that a repair can be completed on the system.
Additionally:
• The initial paver resetting and tree well grates portion of the project has been
completed.
• The enhanced wayfinding signage and sound system installation portions of the
project will be completed during the summer of 2026.
• Update and amend the Peace Plaza Ordinance to create an ADA Pedestrian Access
Route that remains an obstruction free walking zone at all times.
Risks to Scope, Budget, Timeline, or Delivery
None at this time.
Upcoming Requests or Decision Points
Decision to fund, or not, any portion of the repairs of any substantial defects discovered
through the subgrade assessment work.
DMC Alignment
This project directly supports DMC strategic priority of designing for well-being by
imbedding spaces that promote health and wellness in the downtown through the
promotion of social interaction and physical activity. East Peace Plaza is a space where
the broader Rochester community can gather, dine outdoors, and play. The City and
DMC work in partnership with the Rochester Downtown Alliance to activate and
program this space to enhance the experience.