HomeMy WebLinkAboutDMCC Resolution No. 197-2026 (Approving Amendment to the 2026-2027 Five Year Capital Improvement Plan to Provide for Public Realm Infrastructure and Reallocating Funds)DESTINATION MEDICAL CENTER CORPORATION
The following Resolution was offered by Mark Thein, seconded by Paul Williams.
A. On September 25, 2025, the Destination Medical Center Corporation (“DMCC”)
adopted the 2026-2027 Five Year Capital Improvement Plan (the “2026-2027 CIP”) pursuant to
Resolution No. 178-2025.
B. Staff of the City of Rochester (the “City”) and the Destination Medical Center
Economic Development Agency (the “EDA”) have identified a need to address community safety
concerns within the development district boundaries established under the Development Plan
adopted by the DMCC on April 23, 2015, as amended (the “Development Plan”).
C. To address these safety concerns, the City and EDA have evaluated acquiring a
security gate system, in partnership with Mayo Clinic, to enhance public safety during large
community events, for use which shall be prioritized within the development district. The total
cost of the Meridian deployable gate system is $467,300.00, with the DMCC share proposed at
$155,767.00 through a one-third cost-sharing arrangement among the City, Mayo Clinic, and
DMC as further detailed on Exhibit A (the “Capital Project”), which amount was not included
in the 2026-2027 CIP.
D. Pursuant to Resolution No. 196-2026, the DMCC de-authorized and rescinded the
prior approval of a Saint Marys Place subdistrict public realm plan (the “Saint Marys Project”)
and reallocated $500,000.00 originally approved for the Saint Marys Project in the 2024 Five Year
Capital Improvement Plan (the “2024 CIP”) to the 2026-2027 CIP to fund other capital projects.
E. The EDA requests that the DMCC amend the 2026-2027 CIP to incorporate the
addition of the Capital Project to the 2026-2027 CIP and to allocate $155,767.00 of the
$500,000.00 to the Capital Project.
, by the DMCC Board of Directors, that the
DMCC approves an amendment to the 2026-2027 CIP to incorporate the addition of the Capital
Project and to allocate $155,767.00 from the $500,000.00 originally approved for the Saint Marys
Project under the 2024 CIP to the Capital Project, and that the DMCC hereby approves the Capital
Project as a public infrastructure project within the meaning of Minnesota Statutes Section 469.40,
Subdivision 11, and consistent with the Development Plan; provided that:
1. The scope of approval for the Capital Project is set forth in the attached Exhibit A;
2
2.Any material deviation from the scope of approval for the Capital Project will be
subject to subsequent approval by the DMCC, which approval shall be based upon final
determination and review of scope, costs, and availability of funds; and
3.The EDA and City are directed to provide the DMCC Board of Directors with
regular updates with respect to the scope and costs of the Capital Project.
4.Use of the Capital Project shall be prioritized within the development district.
BE IT FURTHER RESOLVED, that the Chair and Treasurer are hereby authorized and
directed to transmit this Resolution to the City and to take such actions as are necessary or
convenient to effectuate this amendment to the 2026-2027 CIP.
42823670v3
The question was on the adoption of the Resolution and there were 7 YEAS
and 0 NAYS, as follows:
BOARD OF DIRECTORS
Destination Medical Center Corporation
YEA NAY OTHER
Douglas M. Baker, Jr. X
Kristin Beckmann X
Kim Norpton X
Randy Schubring X
Mark Thein X
Pamela Wheelock X
Paul D. Williams X
RESOLUTION ADOPTED on May 21, 2026.
ATTEST:
Pamela Wheelock, Chair
Destination Medical Center Corporation
EXHIBIT A
PUBLIC REALM INFRASTRUCTURE
MAY 2026
TO: DMC CORPORATION BOARD OF DIRECTORS
FROM: DMC ECONOMIC DEVELOPMENT AGENCY
Request of the Board
Authorize procurement of public realm infrastructure equipment totaling $155,767.
Approved Project or Program Baseline
• Security Gate System – City, Mayo and DMC Partnership: This system is intended
to enhance public safety for large community events in the downtown area. The total
system cost is $467,300, funding by a proposed one-third cost share between the
city, Mayo Clinic and DMC (approximately $155,767). This shared investment in the
Meridian deployable security system would allow the city to support a professional-
grade, FEMA-compliant solution for events, ensures secure and well-managed
perimeters, and gives organizers and attendees confidence in downtown gatherings.
During non-festival times this system can be deployed to assist in construction
management traffic control in downtown.
• If approved, the funding required for this expenditure would be reallocated from the
$500,000 funding previously allocated to Saint Marys Place public realm planning
and implementation.
Current Status
The Meridian GSA quote has been received and reviewed, with pricing secured through
a federal contract.
Risks to Scope, Budget, Timeline, or Delivery
• The Meridian quote could go up in price or availability due to high demand.
Upcoming Requests or Decision Points
None at this time.
DMC Alignment
Community Safety: The shared security gate system provides the City with a
deployable, professional-grade perimeter management capability for community events,
reducing safety risk and enabling more programming with confidence.
Attachments / Exhibits
• None.